Memorandum submitted by Stroud Town Council
1. The decision of British Waterways to
withdraw from the Cotswolds Canal project has caused considerable
consternation within the local community. Over the last few years
the delivery of the project has raised expectations which it is
difficult to see being delivered without the involvement of British
Waterways.
2. Having submitted an FOI request to British
Waterways it is abundantly clear that British Waterways have not
been committed to the project for at least a year, as a result
of its property development partner not wishing to pursue an interest
in Brimscombe Port. A summary of board minutes and reports is
set out in appendix 1. One of the Board reports in suggesting
an exit strategy states that "much of the blame will be put
down to the cut in grant" (BWB 3274 March 2007). This is
a wholly unacceptable way for a public sector corporation to behave.
3. The real reasons for the failure of this
project are the dependence of British Waterways to profit from
land they have acquired alongside the Canal corridor. As the March
report from the Chief Executive made clear "This very considerable
variance from our previous costings is due almost entirely to
the unravelling of the property transaction assumptions . . .
. In essence we need to realise £1 million per acre for our
developable land and this would only be achieved if we got planning
permission for relatively dense housing . . . . The reality is
that we will not be able to achieve the sort of value we had assumed
in earlier appraisals.
4. From the board report in November 2006
it is clear that part of the "fit with Corporate Policy"
notes that "ISIS has been involved in Brimscombe almost from
the outset and is currently undertaking a capacity study on our
existing holding and the adjacent Brimscombe Mills site (where
there is also developer interest). Isis are expected to confirm
their interest in November." Information on ISIS Waterside
Regeneration can be found at http://www.isis.gb.com/index.html
Presumably the property "unravelling" reported to the
March 2007 board was as a direct result of the work undertaken
by ISIS at Brimscombe Port.
5. The Board report for the January 2008
meeting makes clear that the final straw is the failure of Stroud
District Council to indemnify British Waterways for the repayment
of the Heritage Lottery Fund grant for the whole project (the
whole £12 million) in the event that SDC did not complete
Brimscombe Port. It is wholly appropriate for SDC or any other
partner to be liable for the risk of the part of the project they
are undertaking, however, it is completely unreasonable for either
HLF or BW to expect a minor partner to take on the risk for the
whole project.
6. One of the benefits of British Waterways
being involved in this project is that they have a track record
in maintaining the national canal network and have a track record
in delivering major canal restoration projects. However, it is
clear that British Waterways reliance on property speculation
to fund both the restoration costs and part of the running costs
of the canal has damaged the viability and credibility of the
project. It remains to be seen whether it is possible for the
project to recover from this considerable set back.
Cllr Chas Townley, Stroud
Town Council
March 2008
British Waterways Board Papers
JANUARY 08 BOARD
MINUTES
08/12 Finance Report
On the Cotswolds Canal 1A project, the Board
noted that Stroud District Council would not indemnify BW for
non-performance in constructing the Brimscombe Port section. In
the light of this, together with the funding position generally
and the need to fund the Monmouthshire & Brecon Canal breach
in particular, the board agreed to withdraw from the project.
A full explanation of the reasons for this would be prepared for
funding partners and other stakeholders.
JANUARY 08 - EXTRACT
FROM CHIEF
EXECUTIVE'S
REPORT
"The Board will recall that we had agreed
with Stroud District Council (SDC) that they would construct Brimscombe
Port section of the canal, thereby removing between £2.5-5
million of risk from BW."
"In trying to document this agreement, it
has become clear that SDC will not indemnify BW for non performance.
This means that if SDC do not build out Brimscombe Port to Heritage
Lottery Fund satisfaction, we are liable to HLF clawing back the
whole £14 million grant from us"
"HLF have confirmed that they would be highly
unlikely to do this if we had constructed our part of the canal,
but they will not reqlinquish their right to do so."
"I do not believe we would be required to
pay back the grant by HLF if SDC failed to build Brimscombe although
it remains a risk. What is more likely is that we will come under
great pressure from HLF and others to step in and undertake or
complete Brimscombe Port."
NOVEMBER 2007 MINUTES
Cotswolds
07/136The Chief Executive reported that
issues had arisen with Stroud District Council and HLF which were
further delaying agreement on the commencement of the Cotswolds
1A project. Every effort would be made to achieve an early resolution
of these.
NOVEMBER 2007 CHIEF
EXECUTIVE BRIEFING
6.1 Cotswolds
Despite making it onto the first short, short
list of nine projects (out of an original 300), the Cotswolds
1B project was not selected by the Big Lottery. The Cotswolds
Partnership will now have to consider whether there are any other
options to create this link into the Gloucester & Sharpness
Canal.
SEPTEMBER BOARD
MINUTES
Matters Arising
Cotswolds Canal (Minute 07/90)
07/104The Chief Executive advised that
following a recent meeting with Stroud District Council, heads
of terms for the Council to take on the £3.5 million additional
risk had been confirmed in principle. He was hopeful this would
shortly be translated into a final agreement.
SEPTEMBER CHIEF
EXECUTIVE BRIEFING
PAPER
1. Stakeholder Relations
1.1 Defra Relations
Strategy Day
We had a very constructive Strategy Day with
Defra officials on the 15 August. Sir Neil Cossons facilitated
the meeting and we achieved a common understanding of the financial
pressures/opportunities facing BW. Defra officials were very proactive
in their approach and we definitely further improved our working
relationship.
JULY BOARD
MINUTES
Cotswolds Canal
07/90The Chief Executive referred to
the schedule on the funding position for the Cotswolds Canal restoration
attached to his report. [Confidential information]. Whilst it
had not proved possible to bridge the remaining shortfall now,
all the partners had pledged to continue to work to do so.
The Board agreed that with every possible effort
having been made by the Executive, the risks of proceeding with
the project were now acceptable, assuming that in principle agreements
translated into contracts. The timing of this and announcements
were a matter for the Chief Executive. The special nature of the
project and that it did not create precedents for other restorations
were points to be emphasised.
For the future, it was accepted that meeting
BW's increased commitment would create hard choices in the next
Business Planning round. Identifying a precise restoration budget
for the next 4 year planning period and adhering to it strictly
was a further essential.
JULY CHIEF
EXECUTIVE BRIEFING
PAPER
2.3 Media Relations
The Sunday Telegraph featured a news
report questioning whether the Cotswold restoration would go ahead
or not. It suggested that BW's grant reduction had a direct effect
on the organisation's willingness to pursue additional waterway
miles. We issued a statement reiterating our commitment to the
restoration, but noting that work was underway to reduce the currently
unacceptably high level of financial risk associated with the
scheme.
4.1 Cotswold Canal
We are continuing to make strenuous efforts
to find a solution to the funding gap previously reported to the
Board. The main focus of this work is Stroud Council and the transfer
of responsibility to them for the delivery of Brimscombe Port.
If we can achieve enough comfort on this and cover the relatively
small remaining gap from other funders, we should be able to recommend
continuing with the restoration. However, we may not be able to
achieve this comfort and therefore may be recommending the Board
to withdraw from the project. A verbal update on the position
will be given at the Board Meeting.
Appendix A shows a total income of £28.7
million and a estimate costs of £36.945 million. Potential
solutions are shown as £3.14 million Brimscombe Port Shortfall
to be delivered by SDC? Iron Mills property costs 0.91 million
risk to be underwritten by SDC ? Cost reductions £0.36 million.
Remaining gap £0.834 million after BW increased their funding
from £3 million to £6 million.
BOARD MINUTES
JUNE 2007
07/76The Board considered BW 3281.
On the Cotswolds Canal, it was noted that whilst
efforts continued urgently to bridge the funding gap reported
at the last meeting, the prospects of achieving this were not
good. The Chief Executive confirmed that BW had conveyed this
reality and its consequences to the other funders. It was likely
that a final decision would have to be taken at the next Board
Meeting.
The report reports that "risk workshops
were undertaken with the partners in March. As reported to the
Board in March these workshops identified a project funding gap
of £11 million not least as a result of the property assumptions
made in 2005 unravelling. . . . . SDC are closely involved and
SWRDA have also been advised. . . . We have suggested to Stroud
District Council that they take on responsibility for Brimscombe
Port, including the canal, basins, and the crossing of Brimscombe
Hill Road.
BOARD MINUTES
MARCH 2007
07/42The Board considered BWB 3274.
The Chief Executive advised that the full assessment
of the project risk that the Executive had now completed showed
a project shortfall of £8 million. This was additional to
the £3 million BW had already committed if the project went
ahead. The variance from previous costings was due to the need
to reduce over optimistic assessments of value that could be achieved
from land holdings post canal construction.
The Board expressed disappointment at this unacceptably
high funding gap that had now arisen. It was agreed, however,
that one last effort to bridge the gap should be made. There was
a full discussion on options to achieve this which might be available
to each of the principal funders. An indication of the risk which
might be acceptable to BW was also given. Additionally the Board
considered whether changes in the project scope might be achievable.
The Executive undertook to pursue these issues
and report further. It was accepted that time was pressing but
a short further delay in the decision on whether to proceed was
justified in view of the significance of the restoration.
The board report details the costs and income
and sets out the following:-
"This very considerable variance from our
previous constings is due almost entirely to the unravelling of
the property transaction assumptions. In all previous costings,
the net cost of the property has been used and this hid some over
optomistic assumptions about the value that could be achieved
from our land holdings post canal construction.
In essence we need to realise £1 million
per acre from our developable land and this would only be achievable
if we got planning permission for relatively dense housing. After
full consultation with Stroud District Council, it is clear that
Stroud already have sufficient land allocated for housing to meet
their planned needs and that our land is in the flood plain which
would mean we would have to prove no other suitable land is available.
The reality is that we will not be able to achieve the sort of
value we had assumed in earlier appriasals.
I have met with David Hagg (Chief Executive of
Stroud District Council) and agreed we need to plan for both an
exit strategy and an alternative proposal. (The alternative proposal
was for SDC to develop Brimscombe Port).
Recommendation was to get everything sorted by
end of April and comments "much of the blame will be put
down to the cut in grant. The executive will prepare a comprehensive
PR plan in these circumstances."
NOVEMBER 2006 BOARD
MINUTES
Restoration Report (BWB 3258)
06/158The Board considered a project
submitted for approval.
Cotswolds Canal Phase 1. To restore to full navigation
the canals between Brimscombe Port and Stonehouse and create a
trail between Stonehouse and Saul Junction.
In the discussion, the Regeneration Director
confirmed to Mr Sutherland that he was confident that the Waterway
Trust would raise its commitment of £469,000 over the term
of the project.
The Board accepted there were significant risks,
but on the basis that these were capped and with the project scoring
highly in the core activity of regeneration, it was resolved to
proceed as follows:
BW's total contribution to be set
at £3 million;
The Executive to be tasked to reduce
the current risks of overspend or achieve additional income to
deliver the project within the BW contribution of £3 million;
Approval be given to sign the HLF
funding contract and cash drawn down to commence;
Approval be given for construction
to commence with expenditure subject to clawback limited to £3.2
by March 2007;
The Executive to be instructed to
advise the Board at or before the end of March 2007 that they
can deliver the project within the agreed £3 million BW contribution
and that they are therefore proceeding to completion;
If the Executive cannot reduce the
risks, then BW will not proceed, the project will be abandoned,
recognising the significant reputational risks and the risk of
having to repay £1.6 million of funding.
The report released under the FOI request lists
three property development issues.
"Our Pub Partnership has identified opportunities
at Stonehouse and Brimscombe Port, both on Brownfield sites"
"ISIS has been involved in Brimscombe almost
from the outset and is currently undertaking a capacity study
on our existing holding and the adjacent Brimscombe Mills (where
there is already developer interest). Isis are expected to confirm
their interest in November."
In relation to future maintenance costs it comments
that Gloucestershire County Council has gifted them land which
the District Valuer has valued at £1 million and goes on
to suggest that they are able to realise about £45,000 per
annum from the site (assumed to be Wallbridge) for a pub.
BOARD MINUTES
JULY 2006
06/131The Board considered BWB 3252 and
approved the following projects:
. . . Updates on the following were also noted:
Cotswold Canal Phase 1A and 1B, Droitwich, Liverpool Canal Link,
Manchester, Bolton & Bury and Olympics and Bow Back River
Restoration.
BOARD MINUTES
FEBRUARY 2006
Restoration update (BWB 3210)
06/13The Board congratulated the bid
team on the successful funding applications to the Heritage Lottery
Fund and South West Regional Development Authority (SWRDA) towards
the cost of restoring the Cotswold Canal. The Chief Executive
advised that after careful review, it had been decided that the
SWRDA requirement to pay their funds as capital (ie land) and
not revenue could be accommodated. It was noted that HLF's grant
conditions included Stroud District Council being a co-signatory.
The Chairman undertook to consider an approach
to the Council.
BOARD MINUTES
NOVEMBER 2005
Regeneration projects [BWB 3204]
Progress on the following projects was noted:
The Executive confirmed that linking the canal
to the network was a priority;
BOARD MINUTES
SEPTEMBER 2005
Cotswold Canal Restoration (Minute 05/92)
05/104The Commercial Director confirmed
that the prospects for commercial sponsorship of the canal restoration
had been assessed, but were not significant in terms of the total
funding gap. (See also Minute 05/108).
Cotswolds Canal
05/108The Chief Executive gave an update
on the meeting with major stakeholders on 15 September when the
project funding gap of £9.2 million had been discussed. Mr
Evans advised that the meeting had been constructive, but that
the prospect of increased funding was not good. Several stakeholders
had, however, suggested they might help underwrite the risks.
The possibility of reducing some of the quoted costings for the
works had also been raised. His response to this was that he had
to work on the basis of the costs as they stood unless there was
reliable evidence to do otherwise. If the partners were able to
come close to funding the gap, then he would be prepared to ask
his Board for a contribution.
The Board endorsed the Chief Executive's approach
and that every effort should continue to bridge the gap. It was
agreed that any underwriting of risks would have to be contractually
sound. It was recognised that a potentially most difficult decision
was only a few weeks away.
BOARD MINUTES
JULY 2005
Operational projects (BWB 3194)
05/92The Board considered progress reports
on two prospective projects:
. . . ..
Cotswold Canal Restoration
The Managing Director, South, in introducing
the progress report highlighted the likely £1 million shortfall
in funding which had now been identified together with additional
costs in the order of £5 million. The implications for the
project were fundamental since BW would not be able to fund this
itself, given other competing priorities. Discussions were in
hand with the HLF and SWDRA on funding options. Also every endeavour
was being made to secure voluntary and private sector funding,
although prospects were not good. The Commercial Director referred
to BWs current commercial sponsorship project and undertook to
consider whether it could assist with the Cotswold Canal.
The Board agreed that the downgrading of the
prospects for the project would need sensitive communication to
all involved, internally and externally. It was accepted that
the presentational balance between leading a project campaign
and undertaking the objective assessment of its prospects and
the risks involved was a difficult one. The restoration process
endorsed by the Board at its previous meeting for immediate implementation
would be helpful in that respect.
JANUARY 2005 BOARD
MINUTES
Restoration of the Cotswold & Droitwich Canal;
On the Cotswold Canal, the Board endorsed the
arrangements to take the restoration up to Stage II at no cost
to BW. The Board noted that in the event that it proceeded with
the projects, BW would bear any unfunded elements of both the
Droitwich and Cotswolds restorations. It was felt the implications
of accepting this risk should be considered further in terms of
achieving strategic business planning objectives and especially
greater self-sufficiency and achieving the vision. Middlehaven
was also relevant in this context. There would be a further discussion
at the next Board Meeting.
Stroud Town Council
March 2008
|