Memorandum submitted by Hesco Bastion
(FL 88)
INTRODUCTION AND
SUMMARY
1. Hesco Bastion welcomes the opportunity
to submit evidence to the Select Committee as part of its inquiry
into flooding.
2. The submission covers four areas:
Background to Hesco Bastion
Our role and involvement in the emergency
response to the July floods
Effective emergency response planning
for the future
Planning for the longer term security
of the country's critical infrastructure
ABOUT HESCO
BASTION
3. Hesco Bastion Ltd (HBL) is a Leeds-based
company, founded and owned by Jimi Heselden OBE. The company,
which has been in operation since 1990, has three manufacturing
sites in Yorkshire. It employs approximately 250 people in the
UK and also has a small factory in Louisiana, USA. It has been
involved in civil, peacekeeping, military, humanitarian and engineering
projects for over a decade.
4. HBL manufactures a patented product known
as the Hesco Concertainer® unit, developed to provide the
optimum solution for a wide range of protective and structural
requirements. The system was originally used in civil engineering
and to combat coastal erosion but since then it has also been
deployed in countries such as Iraq and Afghanistan to build blast
mitigation walls; to upgrade levees in the aftermath of Hurricane
Katrina; in the construction of humanitarian shelters and most
recently to protect vital utilities in Gloucestershire from further
flood damage.
5. The Concertainer system consists of linked
welded mesh cells lined with geo-textile. The units, which are
flat-packed and transported to site on pallets, can be pulled
out very easily in a matter of minutes to form a robust barrier
in nine different sizes up to 7" high. The units are then
machine-filled with aggregate to form a robust defence wall. Once
the initial layer is built the wall can then be increased in height
by the addition of further layers. This provides the ability to
tailor the wall dimensions to what is required.
6. The principal effect of this innovation
is the speed at which it can be installed. A typical wall of Concertainer
units, equivalent to 1500 sandbags, can be erected and installed
by two people using a standard front end loader in 20 minutes.
A similar wall made with sandbags would take ten people around
seven hours to build.
7. In an emergency situation, when there
is a threat of flooding, it is essential to move swiftly to protect
the key infrastructures that provide the community with critical
support functions such as power, drinking water and health services.
THE JULY
FLOODS
8. Hesco Bastion Ltd was approached to provide
immediate defence by the emergency planners and utility companies
to protect:
Walham Switching and Power Station,
Gloucester
Mythe Water Treatment Plant, Tewkesbury
Castle Meads Sub Station, Gloucester
Walham Switching and Power Station, Gloucester
9. The National Grid facility, which provides
up to half a million people with power, was flooded on Sunday
22nd July. A temporary installation was erected immediately but
when a second flood warning was issued, Hesco Bastion was called
in to assist the Royal Air Force and the Army with the installation
of the Concertainer Unit. News footage showed flood waters just
inches away from devastating the sub-station presenting a very
real threat for National Grid.
10. The barrierwhich was approximately
800 metres in lengthwas securely positioned in just 19
hours, averting a potential national disaster and ensuring that
power remained on for local residents.
11. Traditional defence walls made of sandbags
could have taken around one week to complete.
Mythe Water Treatment Plant
12. The treatment plant, owned by Severn
Trent Water, was flooded on Saturday 21st July.
13. The facility had been off-line for one
week with the result that 300,000 local residents had lost their
normal supply of clean water Although the clean-up was progressing,
the plant had a limited distribution of non-potable water and
a second flood warning was issued. It was at this point that Hesco
Bastion was contacted and asked to provide emergency flood protection.
14. The units were ordered at 18:00 on Friday
27th July and arrived on site at 21:30 on the same evening. Working
with the Army and local companies, over a kilometre of flood defence
barriers over a metre high were erected around the perimeter in
just 27 hours. Traditional defence walls made of sandbags would
have taken about two weeks longer to complete.
Castle Meads Sub Station, Gloucester
16. Owned by Central Networks (part of E.ON
UK), the sub station supplies electricity to 48,000 homes.
17. It was flooded on Sunday 22nd July and
temporary flood barriers were erected. Once the water levels had
subsided, Hesco Bastion was called in to conduct a site survey.
Although this facility was not under immediate threat of re-flooding,
Hesco Bation provided approximately 300 metres of Concertainer
units to provide a longer term flood defence system against future
flooding.
18. The key benefits of Hesco Concertainer
units compared to the use of sandbags are:
the provision of superior protection
against flooding. The protective walls around the plant are far
more robust than traditional sandbag wallsfewer joints
mean less opportunity for the water to seep through and the linked
structure provides an extremely stable barrier against the possibility
of future flooding.
a much lower skill set is required
for effective assembly of the units compared to the fairly high
skill set required to build effective sandbag walls
the relative speed at which the barriers
can be erected in an emergency
the ability to make structures which
have been put in place for the longer term, more aesthetically
pleasing by the use of foliage and planting to blend it into the
environment
the additional benefit of anti-terrorist
protection
19. Taking into consideration the intensive
labour required to erect sandbag defence walls, the cost of Concertainer
units are comparable.
EFFECTIVE EMERGENCY
RESPONSE PLANNING
20. Fortunately, the secondary flooding
did not materialise in either Gloucester or in Tewksbury.
21. However, the experience does demonstrate
that in emergency situations and within a relatively short space
of time, it is possible to put in place robust flood defences
on a large scale to protect critical infrastructure. In Mythe
for example, with less than 24 hours of planning and 24 hours
of construction, a wall just over one metre high and just under
1 km long was erected.
22. Based on our recent experience in the
UK and from other experiences around the world, we have identified
the following as the significant factors which determine the effectiveness
of an emergency response:
a detailed emergency plan in place
which has been communicated, rehearsed, regularly reviewed and
revised
the existence of a clear decision
making process
a coherent project management team
with clear lines of responsibility and the authority and ability
to procure material in a timely manner
a supply chain in place
a technically competent and motivated
team on site who understand the effect of success or failure
detailed, timely and accurate information
on the likely timing and level of the flood being communicated
to the team on site
availability and allocation of resources
(people, priority access to the site and equipment)
23. Our experience is that while almost
all critical infrastructure facilities have emergency procedures
in place for a fire or a terrorist incident, it seems that no
such procedures exist for flooding. Similarly, while critical
facilities are generally acutely aware of the risk posed to them
by fire or terrorism, it is rare for a risk assessment to have
been made on flooding. Although the recent floods and the associated
media coverage have raised levels of awareness of this, there
is still much work to be done in educating and informing people,
businesses and organisations on the risks and threats of flooding
and the prevention options that are available.
Planning for the longer term security of the country's
critical infrastructure
24. Working with the utility companies,
emergency planners and the Armed Forces, and as long as the necessary
capacity and resources are available, Hesco Bastion can help to
provide an effective emergency response. However, there is obviously
a limit as to how many facilities can be supplied and protected
under an emergency scenario.
25. A much more desirable position is one
where the country's critical infrastructure is not solely dependent
on an effective emergency response, but rather reasonable steps
have been taken in advance to protect key sites from flooding.
26. Such an outcome might be achieved for
example by the following approach:
identify critical infrastructure
at risk of flooding
issue flood risk information and
warning directly to all relevant critical infrastructure sites
and utility companies
companies and organisations obliged
to commission a survey of their facilities and make an assessment
of the risk
companies and organisation obliged
to react and take necessary steps in a timely manner if a risk
is found.
27. Depending on the nature of the risk,
the necessary steps might include stockpiling barriers and materials,
putting project teams on standby or even erecting defence barriers.
28. For some facilities where there is a
more regular or more serious threat of flooding, more permanent
defence protection should be considered. Many such critical infrastructure
sites also carry a risk of terrorist attack and the Concertainer
units double up to provide anti-terrorist protection.
SUMMARY
29. Hesco Bastion's area of expertise lies
in the design, production and supply of the Concertainer units.
The company is not an emergency response planning agency nor is
it a project management company. However we have had first hand
experience around the world in this field and our intention and
hope is that this submission will contribute in some way to improving
the UK's response to the growing threat it faces from flooding.
Hesco Bastion
September 2007
|