Summary
Between 2001-02 and 2005-06, the Home Office spent
£29.1 million planning and designing a purpose-built accommodation
centre for asylum seekers at Bicester. It was an innovative pilot
project and formed part of a wider Home Office initiative to cope
with rising numbers of asylum applications by speeding up the
processing of asylum claims and reducing the social tensions and
the risk of fraud inherent in the way that asylum seekers were
dispersed around the UK.
Falling numbers of asylum applicants, a rise in the
projected net cost of the planned facility at Bicester, and a
general improvement in the speed of processing asylum applications
under the existing system, led to the cancellation of the Bicester
Centre and the shelving of the wider accommodation centre policy
in June 2005. As the project was cancelled before building work
began, the only benefit to the taxpayer is the semi-derelict site,
valued at some £4.6 million, which remains in the Home Office's
ownership.
The strength of opposition to the proposed accommodation
centres from national refugees groups and local resident groups,
which was identified during the passage of the Nationality, Immigration
and Asylum Act 2002, was not fully reflected in the business case
for Bicester. The business case also did not take into account
the potential adverse impact on cost and delivery arising from
a protracted planning delay. The decision by the Home Office to
sign the contract with its preferred bidder before completing
the outline and detailed planning processes increased the risk
of nugatory expenditure.
The lessons to be learnt from Bicester have wider
application to government bodies planning innovative projects.
These lessons include: the need to strengthen corporate governance
arrangements where consultants are engaged at an early stage,
to co-ordinate policy changes in different parts of an organisation
together with consideration of external events, and to increase
the effectiveness and scope of consultation with the local community
and other stakeholders.
On the basis of a Report by the Comptroller and Auditor
General,[1] we examined
the Home Office on the reasons why the cancellation of the wider
accommodation centre policy resulted in nugatory expenditure of
£29.1 million being noted in the Home Office's financial
statements. We also examined the potential future use of the Bicester
site.
1 C&AG's Report, The cancellation of Bicester
Accommodation Centre, HC (Session 2007-2008) 19 Back
|