1 Mitigating the risks to value for
money
1. Between 2001-02 and 2005-06, the Home Office
planned and designed a purpose-built accommodation centre for
asylum seekers at Bicester. It was an innovative pilot project
and formed part of a wider Home Office initiative to cope with
rising numbers of asylum applications by speeding up the processing
of asylum claims and reducing the social tensions and the potential
for fraud which were inherent in the asylum dispersal system at
the time. Of the £33.7 million spent by the Home Office on
the wider accommodation centre project, around £29 million
was spent on designing and planning the Bicester centre and £4.6
million on site searches at up to 40 other locations. The Department
accepted that the accommodation centre policy had not worked.
No development took place at the Bicester site and the site is
now semi-derelict.[2]
2. When preparing the Bicester business case,
the project team assumed correctly that the application for outline
planning permission would be referred to a local planning inquiry.
The team did not, however, consider the likely impact of a judicial
review on the cost and delivery of the scheme. Planning delay
was a major risk to this innovative but controversial project,
requiring strong project management and monitoring to mitigate
the rising costs and falling potential benefits that could arise
from deferring work on site once the contract had been let. That
the business case did not fully recognise these risks was surprising,
given that the Home Office bought in specialist planning consultancy
advice.[3]
3. In December 2003, the Home Office Gateway
3 Review set the status of the project as Red because the case
for accommodation centres had not been developed into a fully
articulated programme.[4]
The Gateway Review concluded that the Bicester business case needed
updating with the latest cost estimates and benefit assumptions,
as well as for the policy developments and performance improvement
measures introduced since the project was first announced. In
February 2004, when the project team submitted the business case
to the Home Office's Group Investment Board, the Board asked the
project team to amend it to include wider benefits, such as faster
removal of unsuccessful applicants. When the full business case
was resubmitted to the Group Investment Board in May 2004 with
the results of the benefits realisation exercise included, no
mention was made of the policy developments or the performance
improvement measures.[5]
4. From the outset, the benefits forecast for
the Bicester accommodation centre never outweighed its expected
costs. In May 2004, the Department's Ministers and Accounting
Officer were briefed by the Project Sponsor that Bicester did
not constitute value for money if only the most narrow and easily
quantifiable benefits were taken into account. The January 2004
business case calculated the net present cost of the project,
excluding benefits, at £179 million (around £18 million
a year at non-indexed prices). Only high level work had been carried
out on potential benefits, which were heavily qualified and estimated
at around £10.6 million a year at non-indexed prices. The
more detailed benefits realisation exercise carried out in May
2004 identified savings from narrow benefits of £22.3 million
a year for Home Office and the National Asylum Support service
budgets, as well as broader benefits for both organisations of
£18.1 million. Not all of the narrow benefits identified
were true savings or efficiency gains in the sense of being "cashable",
and the nature and timing of the broad benefits were probably
unrealistic, given the other measures in hand to speed up asylum
applications. Even with these broad benefits, the cost of the
project still exceeded the forecast benefits by £39 million,
or some £4 million a year.[6]
5. Operationally, the Home Office expected Bicester
to provide a more economical and efficient means than the existing
system of processing asylum applications and housing applicants.
The Home Office treated these efficiencies as benefits and quantified
them in money terms. The business case was based on a broader
set of estimates about the benefits. These benefits included an
estimate of the impact on the overall budget of dealing with asylum
applications more quickly, of not having to house them for so
long, and of being able to deport unsuccessful applicants more
quickly. The business case did not state the actual cost of asylum
applications under the existing arrangements. Nor did it explain
how the potential efficiencies would be derived. The Home Office
told us that the exclusion of this analysis was because of the
Department's belief at the time had been that it was not possible
to establish accurately enough how much it cost to handle an asylum
application. The Department considered that other unquantifiable
benefits were likely from the use of accommodation centres, such
as the impact on putting asylum applicants in one place, rather
than dispersing them into local communities.[7]
6. The Home Office employed agency staff to act
as procurement and financial advisors on the project (Figure
1). Over five years, it paid over £1 million to buy in
these skills, which it did not have in-house. Whilst the use of
agency staff met the Department's short term needs, recruitment
of staff with appropriate skills would have been a better investment.
We endorse the views of our predecessors that key posts on projects
should be held by in-house staff, and that departments should
take a medium to long term look at their recruitment and training
needs.[8]
Figure 1: Details of Home Office Civil Servants
pay (including Agency staff) 2001-02 to 2005-06
| STAFF
| STATUS
| PERIOD WORKED
(MONTHS)
| TOTAL PAID
£'000
|
| Project Manager
| Civil Servant
| 44
| 204.4
|
| Personal Secretary
| Civil Servant
| 38
| 47.8
|
| Deputy Project Manager
| Civil Servant
| 33
| 145.1
|
| Procurement Manager
| Civil Servant
| 39
| 173
|
| Communications Manager
| Civil Servant
| 30
| 114.4
|
| Project Support
| Civil Servant
| 36
| 67.4
|
| Procurement Advisor
| Agency Staff
| 32
| 497.9
|
| Financial Advisor
| Agency Staff
| 39
| 614.3
|
| TOTAL
| | | £1,864.3
|
Source: Home Office
7. Whilst a project of the size and complexity
of Bicester required expert input, the Home Office failed to demonstrate
to this Committee that it had a firm grasp on the risks associated
with the appointment, use and management of consultants expected
of a major government department. It did not analyse payments
made, such that it cannot now say how much was spent on each site
search. It has had to rely on apportionment of costs between Bicester
and other sites, as it did not record this information properly
at the time. Nor could it demonstrate that its consultants added
value by helping the Department mitigate risks arising from the
nature of the project. In all, £6.3 million of the resources
spent on Bicester was spent on consultancy (Figure 2).[9]
This included £0.7 million on planning consultancy, even
though the business case did not anticipate the impact and duration
of planning opposition. It also included around £4 million
on project management, including architects and cost consultants,
even though the Department signed the main contract before obtaining
detailed planning permission, and incurred a £7.9 million
termination payment when the project was cancelled.[10]
Figure 2: Other consultancy payments 2000-01 to
2005-06
| OTHER CONSULTANCY COSTS
| ToTAL (£M)
| BICESTER (£M)
| OTHER SITES (£M)
|
| - Directly attributable to Bicester
- Apportioned
- Other sites
| 0.7
8.2
1.4
| 0.71
5.62
0
|
2.6
1.4
|
| TOTAL
| 10.3 | 6.33
| 4 |
Note 1: Includes
£101,265 for planning
Note 2: Includes £613,266 for planning and some £4
million for professional works advisers including
Core Project Team costs.
Source: Home Office data
8. Bicester accommodation centre was vulnerable
to changes in the trends of people seeking asylum, to unplanned
impacts from other policy changes elsewhere in the organisation
and to operational improvements which reduced the need for the
scheme. These risks were identified in the Gateway 3 Review in
December 2003 but were not acted upon by the Department. The risks
associated with undertaking an innovative project like Bicester
at the same time as changes were being made to the existing application
processing system had not been fully thought through. In addition,
no account had been taken in the design brief of the need to "future
proof" the accommodation by asking the consultants to consider
possible alternative uses for it, should asylum numbers fall.
The Department considered that had Bicester's 750-bed facility
been built, it would have been in use now to house asylum applicants.
It acknowledged, however, that its thinking had evolved in the
period since Bicester was first planned. The Department now favoured
secure detention centres in preference to the open establishment
planned for Bicester, where residents would have been free to
come and go as they pleased.[11]
9. The Department planned and granted the contract
for the design, build and operation of Bicester without considering
the need for an exit strategy. Whilst the contract with its main
contractor, GSL, allowed both parties to walk away at no extra
cost if the project did not obtain outline planning permission,
this was insufficient to mitigate against the risk that the Department
might terminate the contract after outline planning permission
was obtained, but before building work could start. In part, this
exposure and the Department's failure to recognise and consider
its impact on the cost and delivery of the Bicester facilities,
reflected a lack of realism in the Department's business case
assumptions. It was also symptomatic of a wider failure to revisit
the need for the Bicester facilities and to acknowledge the risk
that detailed planning permission might be opposed by the local
planning authority. This omission was to prove costly, and should
have been foreseen, given that the Department employed several
firms of consultants to advise it on planning issues.[12]
2 Qq 10, 38, 86 Back
3
Qq 40-41; C&AG's Report, Executive Summary, para 6 Back
4
Gateway Reviews are carried out on major IT-enabled construction
and procurement programmes and projects. These can be reviewed
at six stages of the procurement lifecycle. Gateway 3 is the Investment
Decision and the OGC Gateway Review methodology defines Red status
as "To achieve success the project should take remedial action
immediately". This does not necessarily mean stop; it indicates
that there are issues which need to be addressed straightaway. Back
5
Qq 13-14; C&AG's Report, paras 17-20 Back
6
Qq 10, 109-112; C&AG's Report, paras 21-24 Back
7
Qq 2-4 Back
8
Qq 117-120; Ev 15 and Ev 17; Committee of Public Accounts, Thirty-first
Report of Session 200607, Central government's use of
consultants, HC 309 Back
9
For details, see Ev 16 Back
10
Qq 19, 41, 46, 99-103, 121-129; C&AG's Report, Figure 11 Back
11
Qq 24-28 Back
12
C&AG's Report, para 28 Back
|