1 Estimating the cost of decommissioning
nuclear facilities
1. In April 2005, the Nuclear Decommissioning
Authority (the Authority) was established to clean-up the UK's
first generation of civil public sector nuclear facilities. The
Authority is a non-departmental public body. It is sponsored by
the Department for Business, Enterprise and Regulatory Reform
(The Department) which approves its strategy and plans. Scottish
Ministers approve its strategy and plans for Scottish sites. The
Authority owns a varied and ageing portfolio of 19 sites (Figure
1).[2] The sites include:
eleven nuclear power stations; four research sites, including
Dounreay (Caithness); a waste repository near Drigg (Cumbria)
and the fuel handling, recycling and production facilities at
Sellafield (Cumbria), the UK's largest nuclear site. Current plans
envisage that the decommissioning and clearance of most sites
will take around 100 years.[3]
Figure 1: Nature and location of the Authority's sites at December 2007

Source: C&AG's report figure 2
2. The Authority discharges its decommissioning
responsibilities through contracts with licensed operators, who
manage each site. These operators are owned by a series of parent
bodies. At February 2008, the parent bodies were British Nuclear
Group Limited (part of British Nuclear Fuels Limited, wholly owned
by government); the United Kingdom Atomic Energy Authority, a
non-departmental public body; Reactor Sites Management Company
Limited, part of the private company Energy Solutions; and Westinghouse
Electric Company, part of Toshiba Group.[4]
3. Since 2003, the estimated
future cost of decommissioning the Authority's sites has risen
significantly. The undiscounted cost reached £61 billion
in the latest plans prepared by the Authority in 2007, an enormous
figure. A further £12 billion[5]
is required to cover the cost of running the Authority's four
remaining operational facilities to the end of their commercial
life (Figure 2).[6]
Figure 2: Growth in estimated remaining lifetime costs of the Authority's sites
Note:
Estimates are for the future undiscounted costs of sites over
their remaining life. Estimates are based on the prices at the
time the lifetime plans were prepared
Source: C&AG's Report, Figure 8
4. Recent increases in the estimates are partly
a result of a more structured approach to preparing lifetime plans.
Prior to the Authority's establishment, cost estimates had been
rudimentary. When it was established, the Authority asked site
licensees to prepare lifetime plans on a consistent basis. Each
plan sets a schedule of the work required to take a site from
its current condition until it reaches its agreed end state, such
as a brownfield site, and estimates the cost of undertaking this
work. As a result, the Authority has gained a better understanding
of what it inherited at each site and how decommissioning work
might be scheduled.[7]
5. Lifetime plans have been refined over five
iterations, and will be updated again in 2008. Costs have risen
after each revision. For example, between 2005 and 2007, like-for-like
costs (after adjusting for inflation and expenditure at the Authority's
sites) grew by £11.7 billion (18%).[8]
6. Rises in cost estimates partly reflect the
uncertain nature of work that will not be undertaken for many
years. Even when the Authority has established full, robust plans,
the estimated cost of decommissioning is likely to be subject
to uncertainty. This is particularly true for work likely to be
undertaken some decades ahead, with the Authority having to make
assumptions about the nature and disposition of wastes, the technology
available and the likely regulatory regime.[9]
7. Elements of cost that might be expected to
be more predictable have, however, also risen rapidly. Between
2005 and 2007, estimates of site support costs such as procurement,
engineering support and human resources, increased by almost £2
billion (9%). And cost estimates for work expected to be undertaken
in the near to medium term (April 2008 to March 2013) rose by
41% over the same period.[10]
8. The Authority identified two reasons for these
increases in cost estimates. Firstly, costs increased as site
licensees filled gaps in their plans, changed decommissioning
strategies and revised cost estimates. Secondly, inflation in
the civil engineering sector and on some raw materials, such as
steel, has been higher than in the general economy.[11]
9. The Authority's scrutiny of site licensees'
planned programmes is limited. The Authority specifies procedures
that site licenses should follow in drawing up plans. Its review
of plans prepared up to and including 2007 focused on ensuring
compliance with those procedures rather than challenging the nature
or cost of proposed work. The Authority has not had access to
benchmark data, nor has it employed independent cost consultants
to review site licensees' estimates.[12]
The Authority is now planning to increase its scrutiny of the
costs themselves. For example, between 2008 and 2011, it is planning
to spend £5 million per annum on obtaining independent advice
on costs.[13]
10. The Authority is unable to predict the final
cost of decommissioning and clearing sites with any certainty.
It expected it to take up to five years to establish a robust
plan and is only part way through this programme. It has yet to
provide a range within which the final figure might fall.[14]
11. The Authority cited the United States' experience
of decommissioning, which suggests that lifetime costs rise initially,
as gaps in plans are removed, and then plateau, before eventually
declining as management of the decommissioning process improves.
The Authority is confident that this pattern will be repeated
in the United Kingdom. For example, it expects that its first
competition to run a site, for the low level waste repository
near Drigg, will deliver a "double digit" reduction
in the cost figures for that facility.[15]
12. The current lifetime plans omit any estimate
for the long-term cost of storing nuclear waste. The arrangements
for the long-term storage of high-level waste have not been finalised.
In 2007, the Government decided that high-level waste, generated
from the reprocessing of nuclear fuel, should be stored in a deep
geological repository. The costs of storing waste will depend
upon the location and design of that repository. The Government
plans to invite communities to volunteer to host the repository
and will launch a consultation in May 2008.[16]
13. In January 2008, the Government published
its White Paper "Nuclear PowerMeeting the energy challenge"
setting out its decision to allow energy companies the option
of investing in new nuclear power stations. The White Paper proposes
"that it will be for energy companies to fund, develop and
build new nuclear power stations, including meeting the full costs
of decommissioning and their full share of waste management costs."
Potential new operators will be required to submit a funded decommissioning
programme for approval by the Secretary of State for Business,
Enterprise and Regulatory Reform setting out:
- the steps operators will take
to decommission their installation; clean up the site and manage
waste (including spent fuel) produced during its electricity generating
life;
- the estimated costs of taking those steps;
- how operators intend to meet those costs; and
- details of the financial security to be put in
place to meet the costs identified.[17]
14. The White Paper proposes that independent
funds, outside of the control of nuclear operators, will be created
to accumulate and manage payments from operators to meet the cost
of decommissioning and waste management. The operator-funded decommissioning
plans will be subject to independent review on behalf of the Department
by a new Nuclear Liabilities Financing Assurance Board. The Government
expects the Board to comprise experts from relevant fields, such
as current or former fund managers, pension trustees, actuaries
and nuclear engineers.[18]
15. There are two important lessons for the Department
from the current decommissioning programme. Firstly, decommissioning
plans should be in place before new facilities are built. The
current facilities, some of them dating back to the 1940s and
1950s, were not built with decommissioning in mind and this has
complicated the task of cleaning-up sites.[19]
Secondly, the Department accepts that there will always be some
uncertainty surrounding the likely cost of decommissioning, and
hence the amounts needed to be put aside to meet this expenditure.
The Department believes that the amounts set aside should be based
on a prudent assessment of these costs. The Department will need
assurance that these independent funds are being properly and
frequently reviewed to assess the likely liability against the
accumulated assets.[20]
16. Ultimately, however, this Committee's past
reports on British Energy show that the Department cannot guarantee
that decommissioning costs will not revert to the taxpayer. Avoiding
such costs would depend on the effectiveness of the protections
to be put in place, in particular, the quality of risk monitoring
procedures established by the Department.[21]
2 The Authority has full ownership of 18 sites and
has a lease agreement with the United Kingdom Atomic Energy Authority
for that part of the Harwell site which was designated to it under
the Energy Act 2004 and requires decommissioning and clean-up.
Back
3
C&AG's Report, paras 1.1, 1.2, 1.7 Back
4
C&AG's Report, para 3 Back
5
The lifetime plan estimate does not reflect the anticipated revenue
from commercial sites. Back
6
Qq 2, 3, 44; C&AG's Report, paras 2.6, 2.8 Back
7
Q 3; C&AG's Report, paras 2.2, 2.3 Back
8
Q 4; C&AG's Report, paras 2.6, 2.8 Back
9
C&AG's Report, para 2.5 Back
10
Qq 5, 91; C&AG's Report, para 2.8 Back
11
Qq 83-85 Back
12
Qq 12; C&AG's Report, para 2.11 Back
13
Q 12 Back
14
Qq 3, 10-11; C&AG's Report, para 2.5 Back
15
Qq 10, 71 Back
16
Qq 55, 78, 82; C&AG's Report, para 1.9 Back
17
Q 97; White Paper (Cm 7296) , paras 1, 3.51 Back
18
Q 46; White Paper, para 3.49 and page 154 Back
19
Q 46; C&AG's Report, para 8 Back
20
Qq 46, 97 Back
21
Qq 24, 25; Committee of Public Accounts, Thirty-seventh Report
of Session 2003-04, Risk management: the nuclear liabilities
of British Energy plc, HC 354, page 4 Back
|