2 Improving delivery of the decommissioning
programme
17. As well as preparing reliable cost estimates,
the Authority must ensure that planned decommissioning work is
undertaken in an effective and timely manner. The strategy
inherited by the Authority for decommissioning individual sites
differs from site to site, affecting the timetable within which
sites will be cleared. The Magnox sites have adopted a 'deferred'
decommissioning strategy. This allows a long period for radioactivity
in the reactors to decay before dismantling them. Resources permitting,
the sites at Harwell and Winfrith could be cleared more quickly,
possibly in 20 years or so.[22]
18. In other countries, some nuclear sites have
already reached the end-stages of decommissioning. By 2004, the
United States had finished decommissioning seven of their former
reactors, and Germany was in the process of demolishing or clearing
the majority of their shut down reactors (Figure 3). At
the same point in time, the UK had one commercial reactor, Windscale
classified as being demolished and cleared.[23]
Figure 3: Shut down commercial reactors by stage of decommissioning at 2004
Source: World Nuclear Association reactor decommissioning database
Note: Not all reactors pass through each of the decommissioning stages
19. The pace of the decommissioning programme
in the UK is dependent on level of resources available and the
priorities faced by the Nuclear Decommissioning Authority. In
2005/06, the Authority's budget was £2,262 million. By 2007-08,
its budget had risen to £2,790 million, of which £2,590
million was expected to be spent on its sites. The figure for
2007-08 was made up of £1,420 million grant-in-aid
provided by the Department and £1,370 million of budgeted
commercial income.[24]
20. In 2006/07, only 31% of the Authority's budget
was devoted to decommissioning project work. Such work includes
defuelling reactors, decommissioning buildings and disposing of
waste. The remainder of the budget is used to meet the cost of
running the Authority's commercial activities, headquarter functions
and site support activities at both its operating and decommissioning
sites. The Authority's expenditure on its commercial activities
is broadly equivalent to the income these activities generated,
so that these activities do not make a net contribution to the
decommissioning budget.[25]
21. In some cases, commercial charges may be
insufficient to cover related decommissioning costs. For example,
the charges levied on customers using the fuel reprocessing facilities
at Sellafield may make a contribution to the cost of decommissioning
those facilities. It is not clear, however, how far these charges,
based on contracts signed by predecessor bodies to the Authority,
reflected the likely actual cost of decommissioning these facilities.[26]
22. Site support activities currently account
for around a third of the Authority's programmed spend across
the 19 sites (£826 million in 2006-07). Such activities
include procurement services, engineering support, human resources
and financial services. To some extent, higher fixed support costs
are inevitable in the nuclear industry because of the licensing
requirements to protect safety, security and the environment.[27]
It is nevertheless possible to introduce efficiencies in support
costs. The Authority plans to cut site support costs by 10% in
2008-09 compared to 2007-08 by encouraging, for
example, the joint commissioning of services such as procurement
and human resources.[28]
23. The overall progress on decommissioning made
to date by the Authority has been hampered by emerging pressures
on its budget, partly due to shortfalls in commercial income,
and by emerging priorities at Sellafield. In its first two years
of operation, the Authority was able to increase the total amount
it spent on decommissioning projects by 12%, from £612 million
in 2005-06 to £686 million in 2006-07. By the
end of 2006, however, the Authority had to cut back expenditure
on decommissioning by £50 million in response to a shortfall
in commercial income. In early 2007, the Authority also made cuts
of £65 million (9%) to the provisional 2007-08 funding
levels for the 14 sites no longer operating.[29]
The Authority made the cuts to fund urgent priority work to clean-up
its high hazard legacy facilities at Sellafield, and to offset
a forecast reduction in commercial income for 2007-08.
Most of these cuts tended to fall on decommissioning activities
as these sites had limited opportunity to cut their support service
costs at short notice.[30]
24. Changes made by the Authority to sites' funding
at short notice have created additional costs for taxpayers. For
example, for 2007-08, the Authority established a fund
totalling £31.6 million to help the sites bearing the largest
reductions in planned programmes to meet the costs of contract
closure as well as staff training, relocation and redundancy costs.[31]
In addition, contractors reported that uncertainties over the
site and composition of the programme might make them more wary
of investing in the decommissioning market. They also reported
that uncertainty could make it difficult for them to retain staff
with the skills in demand elsewhere.[32]
25. There are wide variations in performance
across the decommissioning sites. The Authority's current contracts
reimburse the site licensees for the costs incurred, but allow
sites to earn performance and efficiency fees. They are in effect
cost-plus contracts. In 2006-07, the efficiency fee paid,
for example, as a percentage of budgeted cost of work varied between
zero and 4.6% (Figure 4). The Authority attributes the
variation in performance to differences in culture and organisation
between the sites. In its view, some sites are more innovative
and worked more effectively than others, with the best using multi-disciplinary
project teams.[33]
26. It has also proved difficult for the Authority
to confirm that ongoing efficiencies are carried forward into
future years' lifetime plans. At Sellafield, for example, only
seven of the 80 operating units had been able to build efficiency
savings made in 2006-07 into their 2007 lifetime plans.
The Authority aims to move towards setting longer-term targets
in its contracts to provide a greater incentive to improve performance.[34]
27. The Authority's contracts with site licensees
give it influence over their health, safety, security and environmental
performance, although the sites carry the ultimate legal responsibility
for determining how to comply with regulatory requirements.[35]
28. In 2005-06, the Authority responded
to safety lapses at Sellafield and Dounreay by deducting £2
million from the performance fee payable to site licensees. It
subsequently decided to give licensees the opportunity to re-earn
the fee. Performance has subsequently improved. For example, the
number of accidents involving lost time[36]
at Dounreay fell from eight in 2005-06, to three in 2006-07
and looks likely to fall to two in 2007-08. Similarly,
the international measure of health and safetythe Total
Recordable Incident Ratehas reduced at Dounreay from three
at the beginning of 2006 to a level of 0.3, which the Authority
judges to be world class.[37]
Figure 4: Efficiency fee paid as a percentage of budgeted cost of work performed in 2006-07 by decommissioning site
Note: Sellafield, Dungeness A and Sizewell A have not been included as during 2006-07 their efficiency fee would largely have been determined by their performance in operating commercial facilities. Dungeness A and Sizewell A are both Magnox reactor sites and they ceased generating at the end of 2006.
Source: C&AG's Report, Figure 14
29. The Authority aims to improve the management
and performance of its sites by putting the rights to be the parent
bodies of site licensees out to competition. It also aims to bring
in "world class" management teams to effect the changes
needed. For example, in April 2008, the Authority announced a
new parent body, a consortium led by URS CorporationWashington
Group, to run the low level waste facility near in Drigg. The
Authority also expects to announce the new parent body for the
Sellafield site by the end of 2008.[38]
30. In the Authority's view, the decommissioning
industry in the UK is currently where the construction industry
was 10 years ago, with poor control of overhead costs and poor
project management. In addition, there is no dedicated decommissioning
supply chain in the UK and thus the Authority and its sites are
competing for contractors with other industries such as oil and
gas and civil engineering. The Authority believes that a significant
change in performance can only happen through further development
of the supply chain.[39]
22 C&AG's Report, paras 1.6 to 1.8 Back
23
Qq 28, 33; C&AG's Report, para 1.10 and Appendix 5 Back
24
C&AG's Report, paras 1.12, 1.13 Back
25
Q 43; C&AG's Report, paras 1.14, 3.2 Back
26
Qq 37-41, 43 Back
27
Qq 15, 91; C&AG's Report, paras 2.8, 4.20 Back
28
Qq 15, 91; C&AG's Report, para 4.20 Back
29
The 14 sites comprised nine Magnox sites, four research sites
and a former fuel facility at Capenhurst, Cheshire. Back
30
Qq 60-64; C&AG's Report, paras 3.11-3.14 Back
31
C&AG's Report, para 3.15 Back
32
C&AG's Report, paras 3.16-3.17 Back
33
Qq 34-36; C&AG's Report, paras 1.5, 4.15, 4.16 Back
34
Q 21; C&AG's Report, paras 4.18, 4.23 Back
35
C&AG's Report, para 1.11 Back
36
These are accidents leading to a loss of working time. Back
37
Q 94; C&AG's Report, paras 3.6, 3.9, 3.10 Back
38
Qq 4-5, 98; C&AG's Report, para 1.15 Back
39
Qq 47, 91 Back
|