United Kingdom Parliament
Publications & records
Advanced search
 HansardArchivesResearchHOC PublicationsHOL PublicationsCommittees
Select Committee on Public Accounts Thirty-Third Report


1  Reallocation of costs outside the boundaries of the Major Projects Report

1. The Major Projects Report 2007 provides information on the time, cost and performance of 20 of the Ministry of Defence's largest military equipment projects, where the main investment decision has been taken, and the top 10 projects in the earlier Assessment Phase.

2. The current total forecast procurement costs for the 19 largest military equipment projects (excluding the Typhoon aircraft) is £28 billion.[2] This is an increase of 11% compared with the 'most likely' cost when the main investment decision was taken. The Department is struggling to afford all the equipment it wants to buy and is juggling its budgets as a result. For the second year running, the Department has limited cost increases on its major projects by reallocating expenditure, and sometimes the associated budget, to other areas of Defence spending. In 2006-07, over £600 million was transferred to different budget lines (Figure 1). The Department believes that this reallocation of responsibility for costs will lead to projects being managed better and make measuring performance easier.[3]

3. As some of these reallocations do not represent real savings, they will inevitably impact on other areas of Defence spending. In its Treasury Minute response on the Major Projects Report 2006, the Department agreed it would take steps to identify the impact on other areas of defence where costs are transferred out of the Major Projects Report.[4] The Department has not been able to provide concrete examples whereby the opportunity costs of such transfers are quantified. Instead, it cited:

  • its well-established planning process, through which it balances its acquisition programme within the given budget, including identifying savings that can be made and how their impact can be controlled across all the major military equipment projects on an ongoing basis; and
  • Capability Audits and Balance of Investment Reviews, through which the Department seeks to absorb the costs from the Major Projects Report by reducing investment within the wider equipment and support programme.[5]

4. If no reallocations had taken place, the cost of the Major Projects would be £1 billion more than reported in 2007. While the Department has not claimed these reallocations as savings, they are masking cost increases on projects, in particular, because, in many cases, the money is being managed by the same project teams. This process may help for accounting purposes, for example, in ensuring the total cost of the asset in construction can be easily identified, but after two years, the Department should have identified all the incorrectly allocated budgets and re-assigned them to the appropriate managers.[6]

Figure 1: In 2006-07, £609 million was transferred to be managed either corporately or by other projects and budget holders

PROJECT

EXPLANATION
TOTAL COST TRANSFERREDM)

MANAGED BY
Transfer of costs to other budgets
Support Vehicle
Warranty costs, previously included within the Demonstration and Manufacture phase budget, have been re-categorised to the in-service budget.
-64
The same project team in a different budget line
Sting Ray torpedo
Modifications to the torpedo and conversion costs have been recognised as separate programmes.
-7
The same project team in a different budget line
Transfer of costs to other programmes
Guided Multiple Launch Rocket System
Funding transferred to the Indirect Fire Precision Attack programme, which is in the Assessment Phase project population (Appendix 2).
-165
Different project team which as yet has no approval for the expenditure
Precision Guided Bomb
Reduction reflects the transfer of integration costs to the corresponding aircraft. These projects are currently outside the Major Projects population1.
-67
Tornado and Typhoon project teams
Falcon communications system
Costs associated with the Vehicle Military Engineering Programme transferred to Joint Electronic Surveillance Integrated Project Team.2
-1
Different project team
Measures in line with the Defence Industrial Strategy
Astute Class Submarine
Costs of maintaining a sovereign submarine build capability removed from programme.
-227
The same project team in a different budget line
Type 45 Destroyer
Additional costs, caused by a move of ship build from Barrow to the Clyde.
-78
The same project team in a different budget line
TOTAL 2006-07
####nbsp####
-609
####nbsp####
TOTAL 2005-06
####nbsp####
-448
####nbsp####
MAJOR PROJECTS REPORTS 2006 AND 2007
####nbsp####
-1,057
####nbsp####

Note 1: Typhoon Future Capabilities Programme will be in the Major Projects population for 2007-08

Note 2: This expenditure does not fall within the Major Projects Report population

Source: C&AG's Report, Figure 5, page 13

5. The Major Projects Report 2007 does not provide sufficient information for the Department to be held properly accountable for its expenditure. As a result of the Department reallocating money outside the Major Projects Report boundaries, the cost of the project as reported does not provide Parliament with the full picture of the cost of bringing the equipment into military service. The Department's approach can be likened to an individual only budgeting for the cost of buying a car, and not thinking about the additional initial expenses of being able to use it, or the on-going costs of keeping it on the road. Thus, costs associated with training and logistics are not included within the Department's forecast costs for major projects. Proposed revisions to the format of the Major Projects Report present the Department with the opportunity to correct these omissions and provide us not only with information on the cost of building and procuring the asset, but also making it usable by frontline service personnel.[7]


2   C&AG's Report, para 2. The Typhoon aircraft is excluded from the analysis of costs as the information is commercially sensitive. Back

3   Qq 1, 20-22 Back

4   Treasury Minute on the Forty-sixth Report from the Committee of Public Accounts 2006-2007, Cm 7275 Back

5   Qq 2-3, 6, 45-46, 70; Ev 15 Back

6   Qq 23-24, 26-30, 35, 37-39, 48 Back

7   Qq 34, 73-78, 80 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 22 July 2008