2 Informed decision making by the
Department to deliver value for money
6. The Government requires certain critical defence
technologies and industries to be located in the United Kingdom.[8]
The Department buys submarines and warships infrequently and in
small quantities, and so £305 million of the money reallocated
to other budget lines in the Major Projects Report 2007 relates
to maintaining United Kingdom shipyards. The Department does not
have measures in place to assess whether it is getting value for
money from these payments to sustain the shipbuilding industry
or, if in applying the principles of the White Paper, Defence
Industrial Strategy, it is maximising economic benefit to
the UK from defence expenditure.[9]
7. All of the crucial decisions on projects are linked
to the ten-year forward budgets of the Department's 2008 Planning
Round, which still is not finalised. The Department does not have
enough money to fund all it wants to procure. It appears unwilling,
however, to take decisions to help make the new or relevant projects
affordable, for example, by cutting projects that no longer completely
address the military threats that the United Kingdom faces, or
are many years late. Until the key decisions on resourcing are
taken, publication of the Defence Industrial Strategy 2.0
will be delayed.[10]
8. The future viability of the United Kingdom shipbuilding
industry rests on the contract for the Royal Navy's new aircraft
carriers, as these provide a significant steady stream of work.
The Alliance procurement strategy, a co-operative relationship
between the Department and key contractors and/or suppliers on
a project such as BAE Systems and Thales UK, was announced as
early as January 2003, but additional participants were required.
By July 2007, BAE Systems and VT Group agreed to form a joint
venture to build the ships, and to modernise and manage the reduction
in staff and shipyards after the peak in the next decade. At the
time of our hearing, some 43 weeks later, the Department was close
to the point where a contract could be placed and eventually the
contract was signed by the Department and the industry on 3 July
2008. Past experience shows that delaying projects leads to increased
costs in the long-term.[11]
9. The Department has delayed making decisions and
announcements on other key military equipment projects. The concept
for a new, medium weight armoured vehicles fleet, known as the
Future Rapid Effect System, was drawn up in 2001. A decision on
the preferred design was expected in November 2007, after competitive
equipment trials. Due to the slow progress on this project and
experience on deployments, the Army's immediate need for increased
protection against improvised explosive devices and mines has
been met by additional expenditure to procure foreign vehicles
such as the Mastiff, and by upgrading the British Warrior Infantry
Fighting Vehicle.[12]
10. In 2005, the Department's review of the Guided
Multiple Launch Rocket System showed higher than predicted levels
of accuracy. The Department reduced the quantity of long-range
surface to surface rockets to be procured from 6,500 to 4,080.
It now believes 1,488 rockets will be sufficient for current operations.
Rather than purchasing the remaining munitions, the Department
will use a separate project to examine the potential to develop
other weapons that can provide this military capability. The Department
has, therefore, transferred a budget of £165 million to the
Indirect Fire Precision Attack project. It is sensible that the
Department is able to make trade-offs between projects to provide
the best military response to a threat, reduce overlap and minimise
obsolescence. However, the delivery date for the weapons must
not be compromised by the fact that the Department has not completed
its assessments to determine the types and the balance of munitions
required. Frontline troops must not go short of equipment because
the Department is not yet in a position to approve the main investment
decision for the Indirect Fire Precision Attack project.[13]
8 Ministry of Defence, Defence Industrial Strategy,
Cm 6697, December 2005 Back
9
Qq 18, 53, 55-57, 113 Back
10
Qq 7-8, 40, 42-44, 46, 50-52, 58 Back
11
Qq 12-16; C&AG's Report, Volume II, page 170; Volume I, page
23 Back
12
Qq 9-11; C&AG's Report, Volume II, page 178 Back
13
Qq 4, 83-85, 89-90, 92-93, 95-96, 98; C&AG's Report, Volume
I, page 4; Volume II, page 63 Back
|