2 Overall progress towards the immovable
deadline for the Games
8. The Games will begin on 27 July 2012, and
the bulk of the budget (more than £7,000 million on current
estimates) is for developing the site for the Olympic Park, some
500 acres of previously used and contaminated land in East London.
The Olympic Delivery Authority has reviewed its plans for delivering
the venues and infrastructure, and its November 2007 Programme
Baseline Report details the scope, cost and timings of its projects.[21]
9. Clearing the site for the Olympic Park has
been a priority, and by the end of March 2008, some 80% of buildings
had been demolished and two thirds of the site cleared, enabling
construction to start.[22]
By the same point, the Olympic Delivery Authority had completed
almost a third of its main procurements, but only 23 of the 33
critical path procurements it had planned to complete. The delays
are mainly attributable to the time taken to produce specifications,
obtain planning permissions and negotiate contracts.[23]
10. The contracts for two key Games venues, the
Main Stadium and Aquatics Centre, have been let. The forecast
construction completion dates have slipped by two and four months
respectively.[24] The
Delivery Authority has sought to reduce the impact by arranging
for LOCOG to do work in parallel with construction, in readiness
for test events. Figure 2 shows how the construction timings have
changed on a number of projects since the November 2007 Baseline
was established. Overall, the Delivery Authority still expects
to complete its construction activities during 2011 in time to
allow test events before the start of the Games.[25]
11. Experience from previous Games suggests that
after the Beijing Games the world's attention will turn to London
and this may bring pressure to change venue and infrastructure
specifications. The Department and the Olympic Delivery Authority
acknowledged that they were likely to see demand for changes,
at a time when construction work should be well underway.[26]
Meanwhile the Delivery Authority is working to get its designs
largely agreed before Beijing. Any subsequent proposals will be
scrutinised through the Delivery Authority's arrangements for
change control.[27]
Figure 2: The start and completion dates for the construction of the
main venue and infrastructure projects delivered by the Olympic
Delivery Authority at the end of March 2008 compared with the
milestones in the November 2007 Programme Baseline Report
| November 2007 programme baseline
| March 2008 Forecast
| Change in start date (months)
| November 2007 programme baseline
| March 2008 Forecast
| Change in end date (months)
|
| Enabling Works (site preparation)
| Oct 06
| Oct 06
| 0
| Sept 09
| Sept 09
| 0
|
| Power Lines Under Grounding (switchover)
| Jul 08
| Jul 08
| 0
| Sept 08
| Nov 08
| 2
|
| Structures, Bridges and Highways
| Apr 08
| Apr 08
| 0
| Dec 11
| Dec 11
| 0
|
| Utilities
| Jan 08
| Jan 08
| 0
| Dec 11
| Aug 11
| -4
|
| Main Stadium
| Jul 08
| May 08
| -2*
| Construction end date
Feb 11
Completion date for construction and initial overlay for test events
Jun 11
| Construction end date
Apr 11
Completion date for construction and initial overlay for test events
Jun 11
|
2
0
|
| Aquatics Centre
| Sept 08
| Sept 08
| 0
| Construction end date
Apr 11
Completion date for construction and initial overlay for test events
Jul 11
| Construction end date
Aug 11
Completion date for construction and initial overlay for test events
Aug 11
|
4
1
|
| Velopark
| Mar 09
| Mar 09
| 0
| Apr 11
| Feb 11
| -2
|
| International Broadcast Centre/Main Press Centre
| May 09
| Mar 09
| -2
| Jun 11
| Jul 11
| 1
|
| Olympic Village
| June 08
| May 08
| 1
| Dec 11
| Dec 11
| 0
|
* The planned construction start date on the Main
Stadium was July 2008. The contractors were given access to the
Main Stadium site three months earlier, in April 2008, and construction
work on the site began in May 2008, two months ahead of the planned
construction start date.
Source: Comptroller and Auditor General's Report
HC 490 Session 2007-2008
21 Q 18; C&AG's Report, para 3.2 Back
22
Qq 1, 4; C&AG's Report, paras 3.5, 3.7 Back
23
C&AG's Report, para 3.15 Back
24
Q 17; C&AG's Report, paras 4.20, 4.27; Figure 10 Back
25
C&AG's Report, paras 13, 3.7, 3.9, Figure 10 Back
26
Q 88; C&AG's Report, para 4.13 Back
27
Q 88; C&AG's Report, para 4.13 Back
|