4 Managing within the budget for the
Games
17. In March 2007, the Minister for the Olympics
announced that the budget for the Games would be £9,325 million,[35]
some £5,289 million more than the estimate at the time of
the bid to host the Games.[36]
In our April 2008 Report on the budget for the Games we concluded
that foreseeable requirements for public sector funding were excluded
from the estimates at the time of the bid to host the Games, giving
an unrealistic picture of the expected costs. [37]
18. The Government's response to the Committee's
Report did not accept the Committee's conclusion, arguing that
the estimates at the bid stage were based on the best available
expert advice at the time.[38]
The responses contained in the Treasury Minute and our further
comments are set out in Figure 3.
Figure 3: Committee comments on the Government's response to the Committee of Public Accounts 14th Report 2007-08
| TREASURY MINUTE RESPONSE
| COMMITTEE'S COMMENTS
|
| At bid stage the full form of the delivery body (now the Olympic Delivery Authority) was unknown, as was its tax status.
| Although the tax status of the delivery body was a 'known unknown' at the time of the bid, no provision for potential tax liability was included in the cost estimates at that time.
|
| The projections about private sector income from Partnerships UK were considered robust.
| As we have previously reported, Partnerships UK made clear in 2004 that the information to support a robust analysis of the potential for private financing was not available.
|
| The bid included provision for around £473 million of project contingency, an amount that the Government considered at the time to be appropriate.
| The project level contingency was principally to allow for uncertainties on individual projects. As we have previously reported, the largest single increase in the March 2007 budget was £2,747 million for programme contingency. The programme level contingency is designed to cover programme wide risks such as the interdependency of Olympic projects, the impact of unforeseen ground conditions, changes to legislation, and the availability of materials generic risks which were entirely foreseeable at the time of the bid.[39]
|
| The bid estimate included £190 million for security but this was before the events of 7 July 2005.
| The £190 million was for on-site security during construction, now revised to £354 million, rather than for the separate costs of policing and wider security for which the March 2007 budget included provision based on a preliminary estimate of £600 million. The separate cost of policing and wider security was a 'known unknown' at the time of the bid, but no cost provision was included at that time.
|
Sources: The sources supporting the Committee's
further comments are: Committee of Public Accounts, Fourteenth
Report of Session 2007-08, The budget for the London 2012 Olympic
and Paralympic Games, HC 85: and the C&AG's previous report,
The budget for the London 2012 Olympic and Paralympic Games, HC
612, Session 2006-07
19. The largest part of the March 2007 budget
was the £6,090 million for the Olympic Delivery Authority's
work to deliver the venues and associated infrastructure for the
Games. The budget included a £2,747 million provision for
programme contingency, of which £2,009 million remains potentially
available to the Olympic Delivery Authority (Figure 4).
As LOCOG is intended to be self-financing, its costs are outside
the budget for the Games. The Government is, however, the guarantor
of funding for the Games, which includes meeting any ultimate
shortfall between LOCOG's costs and revenues.[40]
Figure 4: The funds potentially available to the Olympic Delivery Authority
| | | £m
| |
| ODA budget March 2007
| | | 6,090
|
| Total programme contingency provision announced in March 2007
| | 2,747
| |
| Less
| | | |
| Programme contingency made available to the Olympic Delivery Authority (within the March 2007 ODA budget of £6,090 million) (Note)
| 500
| | |
| Programme contingency funds set aside for policing and wider security (non-Olympic Delivery Authority costs)
| 238
| | |
| | | (738)
| |
| Remaining programme contingency potentially available for the ODA
| | | 2,009
|
| Maximum funding available to the ODA
| | | 8,099
|
Note: The Ministerial
Funders' Group agreed allocation to the Olympic Delivery Authority
in two tranches, £340 million in June 2007 and £160
million in November 2007.
Source: Comptroller and Auditor General's Report
HC 490 Session 2007-2008
20. In its November 2007 Programme Baseline Report,
the Olympic Delivery Authority forecast that it would spend £7,095
million, including anticipated use of £1,005 million of the
unallocated contingency. The remaining £1,004 million of
contingency (the Funders' Group Contingency) is to cover residual
risks. An assumption underlying the Baseline estimate was that
£853 million would be saved from scope reductions and efficiency
savings. To that end, the Delivery Authority plans to reduce the
number of temporary venues and, where possible, make use of existing
venues. The Department sees focusing the spending on permanent
facilities as a way of making sure legacy benefits are delivered.[41]
21. By March 2008, the Olympic Delivery Authority's
forecast costs had increased by £16 million to £7,111
million. Decreases in some areas, including £47 million for
site preparation and infrastructure, were offset by increases
in others. The largest increase was £106 million for venues,
including £29 million for the Main Stadium (now £525
million) and £33 million for the Aquatics Centre (now £247
million).[42]
22. The loss of competitive tension in the procurement
processes for both the Main Stadium and the Aquatics Centre has
contributed to the cost increases.[43]
The Government's June 2008 response[44]
to the Committee's report on the budget for the Games[45]
stated that, with the exception of the contract for the Main Stadium,
all main contracts to date have had multiple bidders and effective
competition. The Comptroller and Auditor General's report shows
that in fact the Olympic Delivery Authority had received fewer
than three tenders for nine of the 37 main procurements it had
completed.[46]
23. The Department gave the Committee its unequivocal
assurance that it would stay within the £9,325 million budget
for the Games, despite the uncertainties in the programme.[47]
A difficulty the Olympic Delivery Authority faces is the increased
risk of insolvency amongst the businesses with which it is dealing,
together with inflationary pressures on the costs of energy and
some materials such as reinforced steel. There are also uncertainties
about legacy plans, the costs of policing and wider security,
and the Olympic Village (see paragraphs 5, 7 and 15). The Delivery
Authority acknowledged that it could need to use the Funders'
Group contingency to meet such costs.[48]
The Department is satisfied that the remaining contingency provisions
are sufficient to cover the risks.[49]
24. The budget for the Games is to be funded
by Central Government (£5,975 million), the Greater London
Authority (£925 million), the London Development Agency (£250
million) and the National Lottery (£2,175 million).[50]
The Department's aim is to repay £675 million to the National
Lottery, based on a June 2007 agreement between the Government
and the Mayor of London. The intention is to raise the money from
a share of profits generated by the increase in land and property
values in the Olympic Park. To repay £675 million to the
Lottery, sale receipts will need to reach £1,800 million.[51]
25. In its June 2008 response[52]
to the Committee's report on the budget for the Games,[53]
the Government stated that it had a high level of confidence that,
in view of the time horizon involved, recovery of £675 million
for the National Lottery could be achieved. The recovery of the
£675 million for the National Lottery would require an average
annual increase in land values of around 20%. In its evidence
to the Committee at the end of June, however, the Department acknowledged
that it had not reviewed the assumptions underlying future sales
values in the light of the current property market.[54]
35 HC deb, 15 March 2007, cols 450-452 Back
36
C&AG's Report, The budget for the London 2012 Olympic and
Paralympic Games, HC (Session 2006-07) 612, para 36 Back
37
Committee of Public Accounts, Fourteenth Report of Session 2007-08,
The budget for the London 2012 Olympic and Paralympic Games,
HC 85 Back
38
Treasury Minutes on the Eighth Report and the Fourteenth to the
Fifteenth Reports from the Committee of Public Accounts 2007-08,
Cm 7365 Back
39
C&AG's Report, para 2.5 Back
40
Q 36; C&AG's Report, paras 2.2-2.4, 2.23, 3.26; Figure 3 Back
41
Qq 24-25, 31,35; C&AG's Report, paras 2.5, 2.12, 2.14; Figure
5 Back
42
Q 4; C&AG's Report, paras 2.15-2.16; Figures 5, 6 Back
43
Qq 54, 55; C&AG's Report, Figure 6, paras 4.20, 4.26 Back
44
Treasury Minutes on the Eighth Report and the Fourteenth to the
Fifteenth Reports from the Committee of Public Accounts 2007-08,
Cm 7365 Back
45
Committee of Public Accounts, Fourteenth Report of Session 2007-08,
The budget for the London 2012 Olympic and Paralympic Games,
HC 85 Back
46
C&AG's Report, para 4.14 Back
47
C&AG's Report, paras 4-6 Back
48
Qq 27, 31, 42, 61 Back
49
Qq 7-9 Back
50
C&AG's Report, para 2.19 Back
51
Q 28; C&AG's Report, para 2.22 Back
52
Treasury Minutes on the Eighth Report and the Fourteenth to the
Fifteenth Reports from the Committee of Public Accounts 2007-08,
Cm 7365 Back
53
Committee of Public Accounts, Fourteenth Report of Session 2007-08,
The budget for the London 2012 Olympic and Paralympic Games,
HC 85 Back
54
Q 29 Back
|