Memorandum by Department of Trade and
Industry
The Government welcomes this inquiry and particularly
the Sub-Committee's focus on the practical steps needed to achieve
a move towards renewable energy sources to meet the targets in
the White Paper. It provides an opportunity to explain in greater
detail the work done and in progress since the publication of
the White Paper. We shall endeavour to take account of the views
expressed in the course of this inquiry and of the Sub-Committee's
final conclusions.
The Government's strategy for meeting the 10
per cent renewables electricity by 2010 target has the following
main components:
We have legislated through the Renewables
Obligation Order 2002 to incentivise electricity suppliers to
produce an increasing proportion of their output from renewable
sources (or pay the buy-out price)10 per cent by 2010.
We recognise, however, that this Obligation needs to be underpinned
with additional support for those renewable energy technologies
that are not yet commercially competitive.
We are assisting the development
of renewables projects through capital grants schemes which total
nearly £350 million over the years to 2006. Most of that
investment is aimed at the new technologies of offshore wind farms
and energy crops. Other technologies are being supported through
research and development funding.
We have devised a strategic framework
to facilitate a major expansion of offshore wind energy.
Renewables electricity has been exempted
from the Climate Change Levy.
We are developing renewables planning
through issuing updated planning policy guidance and supporting
renewables planning initiatives.
We have created a new business support
teamRenewables UKto help UK industry capture as
much of this market as possible.
Research and innovation investment
will play an important role in ensuring that sustainable technologies
and solutions are developed and implemented which enable the targets
to be met.
Note:
Prior to the implementation of the Renewables
Obligation and the launch of the capital grants schemes, development
of renewable energy in England and Wales was driven by the Non-Fossil
Fuel Obligations (NFFO). NFFO provided a guaranteed market for
electricity generated under each contract and priced at a premium
rate. Scotland and Northern Ireland had implemented similar mechanisms
to promote renewable energy generation within their region. The
Scottish Renewables Obligation (SRO) preceded the Renewables Obligation
(Scotland) Order in Scotland and the Northern Ireland NFFO (NI-NFFO)
applied in Northern Ireland.
By 2005-06, we will work with industry to bring
forward renewables technologies into the marketplace, supported
by well-targeted Government funding. We are currently conducting
a review of renewables innovation spending across Government.
This review will consider the level of Government spend on renewables
innovation to achieve the 2010 target and create options for achieving
the 2020 domestic emissions target and putting UK on a path to
the cutting carbon emissions by 60 per cent by 2050. It will examine
which are the key renewable technologies for the delivery of the
2010 renewables target and the 2020 emissions target, what are
the barriers to the development and deployment of these key renewables
technologies and what Government measures are needed to facilitate
delivery of the targets and aspirations, and the level of resources
needed. We will let the Committee know the outcome of the review
at the end of this year.
Research Council investments of £28 million
for basic and strategic research in support of sustainable energy
will help to identify and develop "whole system" solutions
to meet 2010 and longer term targets. This includes the establishment
of UK Energy Research Centre and National Energy Research Network
(to provide a focal point and greater co-ordination of energy
researchers across the UK). The "Towards a Sustainable Energy
Economy" programme builds on ongoing Research Council investments
in "blue skies research" and in programmes such as SuperGen,
Carbon Vision (in collaboration with the Carbon Trust), the Sustainable
Technologies Initiative and the work of the Tyndall Centre. The
SuperGen programme has provided support for research consortia
in: Marine Energy; Hydrogen Energy & Storage; Networks and
Power Control; and Biomass & Biofuels. Further research consortia
are being established in: Photovoltaic Technologies; Plant Life
Extension Technologies; Fuel Cell technologies; Energy Storage
& Recovery; Distributed Systems; and Organic and Sensitised
Dye PV. In recognition of the socio-economic challenges faced
in developing renewable energy, ESRC has commissioned relevant
work through various programmes including the Sustainable Technologies
Programme and the Centre for Social & Economic Research on
the Global Environment. Details of technologies and related issues
being addressed by Research Council through these investments
in energy research are set out the separate submission from RCUK.
The Committee has indicated an interest in four
particular aspects and the remainder of this memorandum is structured
as a response to these points.
1. COST-EFFECTIVE
TECHNOLOGIES AVAILABLE
NOW FOR
THE GENERATION
OF RENEWABLE
ENERGY, AND
THOSE THAT
ARE LIKELY
TO BECOME
AVAILABLE IN
THE NEXT
10 YEARS OR
SO
Wind Energy
Both onshore and offshore windfarm development
will be critical to the achievement of the Government's 10 per
cent target for renewables generation by 2010. Wind turbine technology
has now evolved to a mature stage and is an extensively deployed
technology having reached fully commercial status. Its technological
status, together with its availability, mean that it will inevitably
make a major early contribution to the Government's renewable
energy targets.
The UK was initially slow to develop its resource,
despite having one of the best wind resources in Europe. However,
since the introduction of the Renewables Obligation in April 2002
capacity has increased significantly and this is illustrated by
the fact that rate of deployment in 2002 was the highest ever
achieved in the UK with over 87.7MW of capacity installed bringing
the total capacity to 522MW. Against this background the BWEA
reported that a total of 525MW won planning permission in 2002,
almost exactly the total amount built during the previous 11 years.
This trend has continued into 2003 with current UK wind energy
capacity totalling 547.6MW with consent having been given to projects,
both onshore and offshore totalling over 900MW. With a total electricity
demand of around 400TWh in 2002, 1,474GWh was supplied by wind
energy, representing 0.37 per cent of total electricity demand.
While wind energy therefore only contributes to 0.4 per cent of
electricity currently, the new projects both approved and in the
pipeline are expected to make up the bulk of the growth towards
the 2010 target.
The major barrier to onshore wind deployment
is in the area of planning with issues relating to civil and military
aviation interests and public perception major contributors. Work
to help understand the effects of wind turbines on radar systems
together and investigation of measures to mitigate the effects
of wind turbines on radar is currently being undertaken. This
is discussed in more detail below.
The major barrier to offshore wind is the higher
cost and uncertainties related to the operating environment. The
Government has put in place a number of measures to address these
issues in the form of offshore windfarm capital grants designed
to bring forward a number of pre-commercial demonstration projects
and an enhanced programme of industry based research and development
being provided under the DTI's New and Renewable Energy Programme.
Research and Development in the offshore area has been particularly
focused on foundation design and installation techniques.
The Government is sharing the risk to meet the
challenge of offshore development. The DTI launched its Offshore
Windfarm Capital Grants Scheme in October 2001 with the aim of
supporting the early deployment of a significant number of offshore
windfarms. The scheme to date has offered £102 million to
assist industry to build the first offshore wind projects with
seven successful developers so far having received grant support
totalling £64 million. The first of those projects, North
Hoyle, off the coast of North Wales, is expected to commission
in November.
Capital grants and the Renewables Obligation
have a big role to play in providing a favourable economic climate
for offshore wind. But it is also important to have the right
planning regime in place. This is not only to ensure that Government
is able to make the right decisions about consent applications
in a timely manner, but also to enable efficient development of
the onshore transmission system to link up to new offshore electricity
generation. The Government is therefore addressing this issue
for the second round of offshore consents. In addition, the Government
will be introducing legislation as soon as the legislative timetable
allows to enable renewable energy development beyond territorial
waters. Draft legislation is currently being prepared. The purpose
of the draft legislation will be to provide a comprehensive framework
to give developers the legal certainty necessary to develop renewable
energy projects beyond territorial waters, and to enable Government
to regulate such development.
Wave and Tidal Energy
Electricity generation from waves and tidal
streams, if it can be successfully developed, offers the prospect
of a more reliable source of renewable energy than wind, the UK
having one of the best marine energy resources available. Wave
and tidal technologies are still further from commercialisation
than other renewable energy sources, with a number of competing
designs.
In general, shoreline wave energy conversion
is technically developed but not fully commercially proven. It
is still some way from being fully competitive commercially. Furthermore,
there is at present insufficient operating experience, and schemes
need to demonstrate long-term performance and reliability. Offshore
wave technology is still mainly at the research and development
stage. Much work is needed to tackle key development issues, reduce
uncertainty and verify the concepts, although the leading developers
are now beginning to progress to large-scale demonstrations of
their technologies. However, the UK has recently made significant
progress with development projects aimed at harnessing the energy
in marine currents with two full-scale demonstrations to date.
Since the Government decided to introduce support
for a wave energy programme in 1999the programme was expanded
in 2000 to include tidal technologiesgreat strides have
been made in the development of marine systems. The DTI has provided
support under the New & Renewable Energy Programme, with in
excess of £12 million having been committed to research and
development in this area. Currently the DTI's programme supports
seven projects which have or will lead to full-scale demonstrations.
It is important that we ensure that this progress is sustained
and that is why a further £7 million has been set aside (subject
to state aids approval and identified need) over the next two
years to support development in this area. The need will be considered
in the course of the renewables innovation review. Additionally,
DTI has provided support of up to £1.2 million towards the
construction of a Marine Energy Test Centre in Orkney. The Scottish
Executive has committed £2.125 million to the centre this
financial year. The centre will be invaluable in the research
& development and commercialisation of marine energy devices.
The centre will commence operation later this year.
Although the development of these technologies
is reducing predicted energy costs, studies have shown that these
costs are still not fully competitive with electricity supplied
from the grid at today's costs. Further innovation is needed to
overcome the technical challenges that hinder this competitiveness.
Although a number of the current developers have plans for large
scale pre-commercial demonstrations of their technologies by 2010
it is unlikely that these technologies would be deployed commercially
on a large scale until later.
Despite these technologies being further from
commercialisation than some others, they do have the potential
to provide a significant contribution to the overall energy mix
in the longer term (post 2010). The Government is determined that
they should play as full a part in the expansion of generation
from renewables as possible.
Hydro
Hydro power is a commercial technology and accounts
for a significant proportion of our renewable output. Total electricity
generated from renewables in 2002 amounted to 11,444GWh, 41 per
cent of which was from large-scale hydro generation. The position
in the UK is one where most of the economically attractive sites
for hydro schemes have already been exploited and highlighted
environmental concerns are limiting the further deployment of
this technology.
Despite this position there is evidence that
there are plans for new hydro and that many existing hydro stations
have been refurbished, improving their output and extending their
operating life by many years, through refurbished hydro up to
20MW capacity being eligible for the Renewables Obligation.
The Government is continuing to fund research
and development under the DTI's New and Renewable Energy Programme,
mainly into the environmental issues connected to hydro schemes:
this is the main barrier to new developments.
Biomass
Unlike some other renewables, biomass is capable
of providing continuous output once a robust fuel supply infrastructure
is in place. However, biomass is burdened by the necessity of
simultaneous development of energy recovery technologies and fuel
supply (eg energy crops). The Government expects the combination
of the Renewables Obligation, capital grants and co-firing to
stimulate interest in bioenergy. This is further supported by
grants made available through Defra's Energy Crops Scheme. More
modest grants are available to farmers in Scotland, Wales and
Northern Ireland through the Forestry Commission/Forestry Services
Woodland Grants Scheme. Defra will launch the Bio-energy Infrastructure
Scheme in 2004, following State Aids Clearance.
NFFO Orders in England and Wales relating to
biomass projects have so far delivered around 70MW in operating
capacity. The most significant development is the 36MW straw-fired
plant located near Ely, Cambs. Commissioned in 2000, this is the
largest straw-fired generator in the world. Other bioenergy projects
utilise a range of fuels including poultry litter and agricultural
wastes. Development of projects under NFFO has been disappointing
for a mixture of reasons: most notably availability of fuel supply
(in some energy from waste projects), economics and planning.
We are working with Defra to address these issues.
Despite its recent problems it is hoped Project
ARBRE (Arable Biomass Renewable Energy) in Eggborough, North Yorkshire
will be brought to commercial operation by the plant's new owners.
Following the setback in August 2002 when the plant was put into
administration, there is renewed optimism that the project will
become the UK's first commercial power station to be fuelled entirely
on wood. The project is expected to generate around 8MW exported
to the grid, with a significant portion of locally-grown energy
crops in the fuel mix.
Electricity generation plant fired by a fuel
supply of 98 per cent or more (by calorific value) biodegradable
material is eligible for the Renewable Obligation, regardless
of the energy conversion technology used. The conversion of mixed
waste into fuel oil or gas by advanced conversion technologies
like gasification and pyrolysis is also acceptable under the Obligation,
although Renewable Obligation Certificates are only issued for
electricity generated from the biodegradable fraction. Mass burn
incineration of mixed waste is excluded from the Renewable Obligation.
Eligible biomass fuels are confirmed in the Obligation.
To help encourage the development of energy
crops, the co-firing of biomass with fossil fuels, subject to
inclusion of energy crops from a specified date, is permitted
under the Obligation. We are currently out to consultation on
our proposals for the revision of the detailed co-firing provisions
and this consultation closes on 21 November. The proposed changes
aim to get our co-firing and energy crops policy back on course,
without destabilizing the Renewables Obligation. The consultation
paper is at http://www.dti.gov.uk/energy/renewables/policy/roorderamend2003.pdf
The Bioenergy Capital Grants Scheme was launched
in February 2002. The £66 million scheme, jointly funded
by DTI and the National Lottery's New Opportunities Fund, was
competitive and over-subscribed. Twenty one projects have been
offered grants under the scheme, which range from the installation
of heat cluster technology and small-scale combined heat and power
(CHP) with electrical output less than 1MW, to larger scale projects
over 20MW deploying state-of-the-art thermal combustion and advanced
conversion technology. It is not known yet whether all these grants
will be taken up. A priority of the scheme is to increase usage
of energy crops, which must account for at least 50 per cent of
the fuel mix in some technology areas. Under the DTI tranche,
developers are required to spend the grant within three years
once all consents are in place. Developers offered support by
NOF have until 2010 to execute spend.
Support for fundamental research and development
is set to continue through the £19 million DTI's New and
Renewable Energy Programme at least up to 2004-05. Already, the
programme has supported important work to expand our knowledge
of energy crops and advanced conversion technologies and grants
will be offered to new projects that will further the potential
of biomass.
Photovoltaics
Photovoltaics (PV) are not yet cost-effective
in the UK, except in a number of niche applications, eg navigational
aids, remote monitoring, consumer products, but by the end of
the 10 year Major PV Demonstration Programme in 2012 it is hoped
that they will be approaching commercial viability in building
related applications. The PIU Renewables Strategy Review estimated
that costs might have fallen to 16p/kWh by 2010, which would give
a reasonable payback period to consumers.
Potentially any south facing roof or wall could
be used for PV, but the practical resource is limited by the amount
of shading and other obstacles. Even so, the available roof/wall
space is sufficient to generate 75TW hours per year. Only a fraction
of this resource has been used to date because of the cost of
the technology, and barriers such as planning and connection which
are now being addressed.
Fuel cells
Fuel cells are an energy conversion technology
which may utilise renewable or non-renewable sources of energy.
Fuel cells generate electricity from the electrochemical reaction
between hydrogen and oxygen, with water vapour as the only waste
product. The oxygen is usually taken from the air. The hydrogen
may be generated from the reformation of fossil fuels such as
natural gas or by the electrolysis of water. Some types of fuel
cell are capable of carrying out reformation internally, without
the need for a separate reformer, and may be regarded as running
directly from natural gas. Other types may use methanol as a fuel.
If hydrogen is generated from electrolysis and the electricity
is generated using only renewable energy sources the result is
a carbon free energy chain, often referred to as "the hydrogen
economy".
Fuel Cells were discovered in 1837 by Sir William
Grove and successfully used in the US space missions of the 1960s,
but their high costs have precluded terrestrial application until
recently. Although costs of the stack and the associated balance
of plant need to come down significantly there is growing acceptance
that the long promised commercialisation phase is finally underway.
However the timing is very dependent on both the type of fuel
cell technology and the application. Niche, high value stationary
power applicationsremote power and uninterruptible power
supply (UPS) are beginning to be commercial in some parts of the
world. Portable power supplies where fuel cells would replace
batteries in consumer products such as mobile phones, laptop computers
and power tools are expected to be introduced within the next
two to three years. In both these areas there is a clear consumer
benefit in terms of the availability and reliability of power
which would justify the higher price.
The first "mainstream" application
for fuel cellswhere the price of the power would need to
be competitive with conventional alternativesis expected
to be stationary power or combined heat and power (CHP) generation.
Applications are envisaged at the micro levelindividual
householder systems, as well as larger systems (200kW1MW)
for blocks of flats, commercial and industrial properties. This
would be distributed generation, where the electricity would be
generated near the point of use (avoiding transmission losses).
Such systems are currently being demonstrated (particularly in
Europe) and fully commercial systems are expected within the next
five years.
There is some potential interest in the use
of fuel cells coupled with electrolysers as a means of energy
storage for intermittent renewables such as wind or photovoltaics,
but success would be critically dependent on the economics.
The use of fuel cells to replace the internal
combustion engine in passenger cars represents the greatest techno-economic
challenge faced by the technology, and most industry experts do
not expect to see significant penetration of fuel cell vehicles
to occur before 2015-20. Limited demonstrations, particularly
of buses and depot serviced urban delivery vehicles are likely
before then and a limited market for such vehicles could develop
if assisted by regulation on urban air quality.
Fuel Cells UK was launched in May 2003. It will
help the emerging UK sector by helping promote and raise the profile
of the fuel cell industry in the UK. It will also act as a central
contact point for national and international companies and the
research community. It will be led by a steering group including
representatives from leading UK fuel cell companies, Government
and academia. Fuel Cells UK will work closely with new and existing
initiatives in the UK and across the world.
2. THE NUMBER
OF SITES
POTENTIALLY AVAILABLE
FOR SUCH
TECHNOLOGIES, AND
THE OBSTACLES
TO TAKING
THESE UP
IN TERMS
OF PLANNING
AND OTHER
CONSENTS
Planning
The Office of the Deputy Prime Minister expects,
in October, to consult on draft planning guidance for renewable
energy projects (Policy Planning Statement 22) in a consultation
exercise. During the consultation process, we will develop a good
practice guide for planning authorities as a companion volume
to PPS 22. The final version of PPS 22 will be published in May
2004, to encourage local authorities and developers to use renewables
and encourage a strategic approach to the deployment of renewables
projects in the regions.
The Scottish Executive has already revised Scottish
planning guidelines NPPG6 in 2000 and PAN45 in 2002 to give clearer
advice to renewables developers.
Scottish Ministers will be consulting later
this year on the consents procedure for developments of over 50
MW under Section 36 of the Electricity Act 1989 in order to improve
the process.
Similarly, the National Assembly for Wales has
revised Welsh planning guidelines for renewable developers. Planning
Policy Wales was issued in March 2002. A Tripartite Working Group,
involving officials from the DTI, the Wales Office and the National
Assembly for Wales is currently evaluating the bid by the National
Assembly for Wales for the consenting powers under section 36
of the Electricity Act 1989 to be transferred from central Government
to the devolved administration.
Statistical information on planning
We are working to improve statistical information
on renewables planning in the UK. There are currently two main
sources of Government statistics on the status of planning applications:
information collected as part of the DTI's renewables programmes
scheme and information collected by the DTI and the Scottish Executive
on consents given under Section 36 of the Electricity Act and
(for England and Wales) the Transport and Works Act 1992.
The information from the DTI's renewables programmes
scheme is collected under two main categoriesNFFO and non-NFFO.
These categories cover most of the applications made under planning
procedures for onshore renewable technologies. Total figures given
in Table A below show the current status (approved, refused, withdrawn
or to be determined) of onshore applications made in the years
2001, 2002 and 2003 in the UK.
Information on the progress of applications
for all offshore and some onshore technologies is categorised
under Section 36 Onshore, Section 36 Offshore and Transport and
Works Act 1992 Offshore. Applications for onshore developments
of over 50MW are considered under Section 36 of the Electricity
Act 1989. Offshore developments over 1MW require consent either
under Section 36 of the above Act or the Transport and Works Act
1992. The Transport and Works Act applies in England and Wales
but not Scotland. Table B below gives information on the current
status of applications made under these Acts.
For the three years in question, the success
rate for NFFO (SRO & NI-NFFO) projects is highest in Scotland
(73.33 per cent), followed by England (60 per cent), Wales (42.86
per cent) then Northern Ireland (0 per cent). The percentages
for refusals are 8 per cent (England), 0 per cent (Scotland),
42.85 per cent (Wales) and 0 per cent (Northern Ireland).
When considering application success/failure
over the past two to three years, it should be borne in mind that
we are effectively in a transition from NFFO to non-NFFO (in effect,
to the Renewables Obligation in England Wales and Renewables Obligation
Scotland in Scotland. Northern Ireland does not have a Renewables
Obligation in place) applications and many of the latter will
have been submitted, but have yet to be determined.
Table A
INFORMATION FOR THE THREE YEAR PERIOD, 2001,
2002 AND 2003
Scheme under which
project funded
|
Applications submitted |
Applications approved |
Applications refused
|
Applications withdrawn |
Applications to be determined |
NFFO,SRO & NI-NFFO | 47
| 29 (61.7%) | 5 (10.6%) |
Nil | 13 (27.7%) |
Non-NFFO, Non-SRO &
NI-NFFO
| 158 | 62 (39.24%) | 16 (10.13%)
| 4 (2.53%) | 76 (48.10%) |
| |
| | | |
Table B
INFORMATION FOR THE THREE YEAR PERIOD, 2001, 2002 and
2003
Consenting authority
|
Applications submitted |
Applications approved |
Applications refused
|
Applications withdrawn |
Applications to be determined |
S36 Onshore | 4 (England & Wales)
| 1 (25%) | Nil | Nil
| 3 (75%) |
S36 Offshore | 7 including 1 in Scotland
| 7 (100%) | Nil | Nil
| Nil |
Transport and Works
Act 1992 Offshore
| 6 including 1 in Wales | Nil
| Nil | Nil | 100%
|
| |
| | | |
Table C below gives a longer-term view, covering NFFO and
non-NFFO projects, for the period from 1990 to 2003.
For NFFO (SRO & NI-NFFO) projects, the success rate of
applications is highest in Northern Ireland (95 per cent) followed
by England (82 per cent), Scotland (74 per cent) and Wales (61
per cent). The percentages for refusals follow a similar trend
(0 per cent, 10 per cent, 9 per cent, 23 per cent).
Table C
INFORMATION FOR THE PERIOD FROM 1990 TO 2003
Scheme
|
Applications submitted |
Applications approved |
Applications refused
|
Applications withdrawn |
Applications to be determined |
NFFO, SRO & NI-NFFO | 480
| 374 (78%) | 56 (12%) | 19 (4%)
| 32 (7%) |
Non-NFFO, non-SRO &
non-NI-NFFO
| 190 | 83 (44%) | 24 (13%)
| 4 (2%) | 79 (42%) |
| |
| | |
|
Ministry of Defence action
We will report progress on Ministry of Defence action to
improve windfarm approval rates in February 2004. The Ministry
of Defence have already introduced a helpline for developers and
are working to introduce new, faster processing arrangements for
applications. By March 2004, the Wind Energy, Defence and Civil
Aviation Working Group will revise the current interim guidelines
for windfarms into a permanent set of guidelines.
Regional assessments
The initiative for new power station proposals clearly rests
with private sector companies. The Government seeks to set a framework
and create a favourable climate against which proposals needed
by the market can then come forward. The Government seeks to provide
an overview. Of the renewable technologies the most developed
has been hydro and onshore wind energy. In addition to reviewing
the planning guidance the Government has also had carried out
regional assessments. This work by OXERA for DTI identified the
potential of each region and was intended as a starting point
for developing regional targets. Scotland and Wales and some regions
have taken this further and developed sub-regional targets. The
assessments for Scotland and Wales and for each region were:
| TWh by 2010 | % of 2010 10% Target
|
| Scotland | 3.6 | 11.1
|
Wales | 4.4 |
13.4 |
East of England | 4.3
| 13.3 |
East Midlands | 2
| 6.1 |
London | 0.6 |
1.9 |
North East | 2 |
6.3 |
North West | 3.2
| 9.7 |
South East | 3.3
| 10.1 |
South West | 2.5
| 7.8 |
West Midlands | 2.9
| 8.9 |
Yorkshire & Humberside |
3.6 | 11 |
| |
|
We expect developers to bring forward proposals against the
backcloth of these assessments; the Government will monitor the
situation. The Government does not identify sites within these
regions and there is no list of potential sites for developers.
Such an exercise would mean the Government assuming a commercial
expertise it does not have and at the same time effectively pre-judging
any subsequent planning application. Inevitably some proposals
will be rejected by the planning system but by building in regional
commitment, by giving a clearer picture of potential and establishing
the role that regional areas can play in creating the low carbon
economy, there is real prospect of shifting the debate from one
of "we need renewables here/we don't need renewables here"
to one of what is the appropriate location. Planning will still
be a concern, there will always be those totally opposed, and
Government will need to continue to work at improving the climate
against which renewables proposals come forward.
The first round of offshore wind farm development could bring
forward 1.5GW of generating capacity if all the projects go ahead.
To date seven projects have received development consent with
a further six projects under consideration. The developers chose
their own site and applied to the Crown Estate for an agreement
for lease which gave them security over the site. These lease
agreements are finalised once the developer has obtained the necessary
consents for the project from the relevant Government Departments.
The experience of the first round showed that developers
are keen to put in place wind farm projects offshore. To optimise
further exploitation of the potential wind resource in a responsible
manner the DTI has adopted the strategic planning framework which
was outlined in its November 2002 consultation document "Future
Offshorea strategic framework for the offshore wind industry".
The main element of this framework is that wind farm development
will be focused in defined areas of the sea. This enables the
potential impact of wind farms in these areas on the environment
and other marine users to be evaluated before being offered for
development. This approach also facilitates greater efficiency
in the provision of offshore transmission cabling which could
be shared by several projects in the same area. The allocation
of sites to developers within these broad areas will be made on
the basis of competitive bidding rounds.
The DTI has selected the Greater Wash, Thames Estuary and
the North West (from the North Wales coast to the Solway Firth)
as having the greatest potential for offshore wind farm development,
based on wind resource, water depth and access to onshore grid
connections. A strategic environmental assessment of these three
areas has been undertaken to assess the potential impact of development
on a range of environmental factors.
As a result of this evaluation the DTI requested the Crown
Estate in July 2003 to conduct a second round of offshore wind
farm site leasing. Developers have been invited to tender for
projects in the three strategic areas but areas of special environmental
sensitivity have been excluded from the tender round, bearing
in mind the much larger scale of development proposals which are
being planned for the second round. This approach has the benefit
of excluding from development sites of particular sensitivity
early in the planning process so that developers do not waste
resources on projects which are unlikely to receive planning consents.
The DTI has commissioned a study of the UK's total offshore
renewable energy resources which encompasses wave and tidal resources
as well as wind. This study will identify other locations which
offer promise for future development and will inform decisions
about future strategic environmental assessment programmes. It
is possible that future licensing rounds for offshore wind farm
projects will be arranged in the three strategic areas which are
currently being offered for development.
Rate of build
Annex A sets out the position on projects for which consent
has been applied. It is not entirely comprehensive but demonstrates
that, taking England, Wales and Scotland together, there are projects
totalling over 3,500MW in the pipeline. Of these, projects totalling
over 2,200MW have received consent, and of those, five projects
with a total capacity of 220 MW are currently under construction.
These include the first two offshore wind farms. As the tables
show, more projectsin particular offshore wind farmsare
expected to start construction in 2004 and 2005.
We are working on a further analysis and this together with
a report on the conclusions of the renewables innovation review
(referred to on page 2) will be sent to the Committee.
Manufacturing and Installation Capacity
We are supporting the development of a UK supply chain in
the renewables sector. The baseline level of employment in the
sector will be determined by a Renewables UK Supply Chain Gap
Analysis, which is underway. This will identify UK renewable energy
industry's strengths and weaknesses, ranking gaps and identifying
priority areas to be addressed by key stakeholders and diversification
opportunities for industry. It will also provide estimates of
future jobs per MW for both mature and emerging technologies,
skills requirements, design, manufacturing and service capability,
investment and R&D needs and other factors that will influence
growth. The report will be released on 18 November and we shall
send the Committee a copy.
Providing the Supporting Infrastructure (Such as Access Roads
and Extensions to the Electricity Network)
The provision of an adequate electricity infrastructure,
both distribution and transmission, is of critical importance
to the application on renewable technologies and the achievement
of the Government's renewable targets and aspirations.
The Government is committed to introducing the British Electricity
Trading and Transmission Arrangements by April 2005 and legislation
will be brought forward as soon as Parliamentary time allows.
BETTA is necessary to enable all renewable generators to have
access to a GB wide market through a transmission system operator
that is independent of generation and supply interests. BETTA
also provides a mechanism to ensure that the costs of investment
in the grid infrastructure, including that needed as a result
of our renewables targets, can be recovered appropriately.
The work of investing in the electricity distribution networks
is being taken forward by the companies, and is being considered
by Ofgem as part of its ongoing work of setting the new distribution
network operator price controls, which will apply from 1 April
2005. The DTI and Ofgem, together with the transmission companies,
have established the Transmission Issues Working Group (TIWG).
The TIWG commissioned two studies that identified significant
infrastructure upgrades that may be required as a result of future
renewables development proposals. The role of the TIWG is also
to identify, well in advance, the issues required to be resolved
in order to meet the needs of the Government's renewables targets.
Much of the renewable generation such as onshore wind, early
offshore wind and biomass, required to meet Government targets
will be connected at distribution voltages, ie 132kV and below.
Currently, distribution networks are designed to distribute energy
from the transmission system to customers, and are not designed
to facilitate the connection of large amounts of renewable and
other small generation. There is a need, therefore, to transform
the passively managed radial nature of the existing distribution
networks into actively managed networks which can accommodate
the bi-directional energy flows and other issues associated with
significant amounts of generation.
Resolving these technical issues will require considerable
innovation by network operators and owners. To encourage this
innovation and overcome a number of non-technical issues, we must
ensure that distribution network operators have adequate business
incentives to connect generation to their networks. In addition,
there is a need to ensure that appropriate connection charging
arrangements are developed so that unnecessary barriers to the
connection of generation are removed. Ofgem are currently addressing
these issues through the 2005 Distribution Price Control review
and their review of connection charging arrangements.
Progress in overcoming existing technical, regulatory and
commercial barriers to the development of distribution-connected
generation is being monitored by the joint DTI-Ofgem Distributed
Generation Co-ordinating Group.
Whereas most renewable generation is likely to connect to
the distribution networks in the medium term, much of this will
be in remote locations and there is a need to ensure that the
electricity transmission network is capable of handling the energy
flows implied. In addition, future offshore developments may be
connected directly to the transmission network via offshore collector
"hubs". The DTI, together with Ofgem and the network
operators, is currently monitoring via the TIWG the development
of the transmission network needed to ensure the achievement of
the Government's renewable targets and aspirations.
3. LOGISTICS OF
PROVIDING STAND-BY
CAPACITY FOR
TIMES WHEN
INTERMITTENT SOURCES
ARE NOT
AVAILABLE
The Government's renewables targets and Energy White Paper
aspirations are likely to be met predominately by wind generation,
which is intermittent in nature. What capacity value should be
assumed for wind generation is the subject of some debate. It
is dependent on the level of penetration.
Key research is continuing on storage technologies that will
support intermittent generation. The DTI is funding research into
the impact of the Regenesys storage technology on facilitating
the integration of intermittent renewables.
The fact that UK wind farms sites are dispersed throughout
the country, and are located in areas with a high wind resource,
will tend to reduce the overall intermittence effects of wind
generation. The additional balancing costs associated with intermittency
will vary with penetrationNGC have recently estimated additional
balancing costs at round £1.5/Mwh and £2.38/MWh for
55 and 105 wind penetration respectively.
It should be remembered that even traditional generating
plants, such as gas or nuclear, undergo occasional shutdowns for
essential maintenance. This type of generating loss is more difficult
to cope with than the intermittency of wind, because the amounts
of electricity involved are typically of a greater magnitude.
When this type of shutdown is compared to the intermittency of
dispersed wind farms, then the variation in output from wind generation
is minimal.
The capacity factors of all generation stations vary, and
are taken into account in estimating the contribution made by
each technology. In the UK, it is estimated that the capacity
factor for wind farms varies from about 35-40 per cent at low
wind penetration to something like 20 per cent for a wind penetration
of 26GW. The capacity values of plant is a significant issue in
determining overall nation plant margin requirements and NGC have
estimated that, maintaining traditional standards of generation
security assuming that 20 per cent of electrical energy requirements
where met entirely from wind, would require a plant margin of
some 49 per cent. The capacity factor of wind generation has little
or no bearing on the energy produced by that generation or its
contribution in terms of reduction in carbon emissions. Energy
produced by wind generation is dependent on availability and load
factor and is not influenced by some notional capacity factor
or contribution.
Analysis for the White Paper shows that the electricity system
could cope with an increasing reliance on renewable generation.
But the study also highlights that as the proportion of intermittent
generation increases, the cost of maintaining stable supplies
also increases. We accept that these costs need to be managed
and new ways found to minimise them. We are already funding research
into this through the DTI's Renewable Energy and the Engineering
and Physical Sciences Research Council's Supergen programmes.
As part of our current capital grant programme we allocated in
2002 an additional £4 million to facilitate the demonstration
of new control, storage and metering technologies.
It will be necessary to ensure that future electricity market
and trading arrangements include incentives to bring sufficient
plant capacity forward in order for reliability of supply to be
maintained.
4. INTERMEDIATE MILESTONES
THAT SHOULD
BE SET
ON THE
WAY TO
ACHIEVING THE
WHITE PAPER'S
AIMS
The White Paper sets out a detailed and long-term strategy
for achieving its objectives including over 130 commitments and
the means for delivering them.
We have published an implementation plan on the Sustainable
Energy Policy Network web site http://www.dti.gov.uk/energy/sepn/index.shtml.
This sets out details on the 10 individual workstreams (one of
which covers renewables) and lists some 100 key milestones for
implementing the commitments in the Energy White Paper as well
as the names and contact details of the officials responsible.
The website is updated regularly to show progress on implementing
the milestones. The White Paper already sets out the steps to
be taken to accelerate the take-up of renewables. We expect the
industry to respond to the framework established by the Government
and demonstrate they can achieve our goals for renewables at an
acceptable cost.
The key intermediate milestones in the renewables workstream
are described earlier in this memorandum. These concern both developing
renewable technologies, and UK capacity, and addressing the barriers
to the deployment of renewables.
We are currently consulting on a technical review of the
working of the Obligation to ensure that the Obligation is working
as originally intended, by focussing on adjustments to the co-firing
rules that allow power stations to burn biomass alongside fossil
fuel in order to increase electricity generation from energy crops
through co-firing. The technical review also addresses the scope
for assisting solar and other micro generators. The consultation
document can be found on the DTI website at www.dti.gov.uk/energy.
In 2005-06, we shall review progress on the Renewables Obligation
and will elaborate a strategy for the decade to 2020, including
the impact of the Emissions Trading Scheme.
Annex A
Information on Renewable Power Stations for which consent
has been applied
(A) ENGLAND AND WALES
Station |
Owner
|
Size |
Type
|
Status | Under Construction
|
(A) Onshore |
| | | |
|
Cefn Croes, West Wales | RDC
| 60MW | Onshore windfarm |
Approved
23/5/02 | Not yet
|
Little Cheyne Court, Walland Marsh, Kent
| National Wind Power | 78MW |
Onshore windfarm | Being processed
| Not relevant |
Scout Moor, near Rochdale, Lancashire
| United Utilities & Green Energy | 65MW
| Onshore windfarm | Just started in process
| Not relevant |
Whinash, near Tebay, Cumbria |
RDC and Falck Renewables Ltd | 67.5MW
| Onshore windfarm | Application just received
| Not relevant |
Total onshore | 270.5MW
| | | |
(B) Offshore |
| | | |
|
Scroby Sands, off East Anglia |
PowerGen | 76MW | Offshore windfarm
| Approved
17/4/02 | Some onshore work started
|
North Hoyle, off North Wales |
NWP Offshore (Innogy) | 90MW |
Offshore windfarm | Approved
31/7/02
| Yes |
Rhyl Flats, off North Wales |
NWP Offshore (Innogy) | 100MW |
Offshore windfarm | Approved
12/12/02
| Not yet |
Barrow, off Walney Island | DONG
| 108MW | Offshore windfarm |
Approved
10/3/03 | Not yet
|
Kentish Flats, off Whitstable |
GREP | 129MW | Offshore windfarm
| Approved
12/7/03 | Not yet
|
Burbo Bank, off Wirral | Seascape Energy
| 90MW | Offshore windfarm |
Approved
9/7/03 | Not yet
|
Station |
Owner
|
Size |
Type
|
Status | Under Construction
|
Inner Dowsing, off Skegness |
OWP | 120MW | Offshore windfarm
| TWA Order2 being processed | Not relevant
|
Lynn, off Skegness | AMEC Offshore
| 108MW | Offshore windfarm |
TWA Order being processed | Not relevant
|
Cromer, off Cromer | Norfolk Offshore Wind Limited
| 108MW | Offshore windfarm |
TWA Order being processed | Not relevant
|
Gunfleet Sands,
off Clacton
| GE Wind Energy | 108MW |
Offshore windfarm | TWA Order being processed
| Not relevant |
Shell Flat, off Cleveleys | Cirrus Energy
| 324MW | Offshore wind farm |
TWA Order being processed | Not relevant
|
Scarweather Sands | United Utilities Scarweather Sands Ltd
| 108MW | Offshore windfarm |
TWA Order, public inquiry pending | Not relevant
|
Total offshore | 1,469MW
| | | |
| |
| | |
|
The table shows approvals from November 2000 (when the stricter
consents policy was lifted) and state of play on applications
for stations over 50MW.
2 TWA Order = Transport and Works Act Order
(B) SCOTLAND
Station |
Owner
|
Size |
Type
|
Status | Under Construction
|
| (A) Onshore | |
| | |
|
Cairn Uish | Natural Power
| 56MW | Onshore wind farm |
Approved
21/1/03 | Not yetConsent to extension applied for
|
Paul's Hill | Natural Power
| 56MW | Onshore windfarm |
Approved
9 April 2003 | Not yetextension applied for
|
Crystal Rigg | Natural Power
| 49MW | Onshore windfarm |
Approved | Completion expected November 2003
|
Edinbane | AMEC |
49.5MW | Onshore windfarm | Approved
November 2002
| Not yet |
Garrogie | Innogy
| 2.0MW | Hydro | Approved
9 April 2003
| Not yet |
Kingairloch | SSE
| 3.5MW | Hydro | Approved
9 April 2003
| Completion Spring 2004 |
Braevallich | Innogy
| 2.5MW | Hydro | Approved
23 March 2003
| Completion Spring 2004 |
Station |
Owner
|
Size |
Type
|
Status | Under Construction
|
Causeymire | NWP |
49.5MW | Onshore windfarm | Approved
November 2002
| Not Yet |
Total onshore | |
268MW | | |
|
(B) Offshore |
| | | |
|
Robin Rigg | SOL/OERL
| 199MW | Offshore windfarm |
Approved
25/03/03 | Starting date Spring 2005
|
(C) Under consideration
| | | |
| |
Hadyard Hill | SSE
| 130MW | Onshore windfarm |
Under consideration | Spring 2004?
|
Windy Standard Extension | Natural Power
| 90MW | Onshore windfarm |
Under consideration | Spring 2004?
|
Black Law | Scottish Power
| 134MW | Onshore windfarm |
Under consideration | Spring 2004?
|
Farr | National Wind Power
| 70MW | Onshore windfarm |
Under consideration | |
Braes o'Doune | Airtricity
| 100MW | Onshore windfarm |
Under consideration | Spring 2004?
|
Clashindarroch | Amec
| 129MW | Onshore windfarm |
Under consideration | |
Whitelee | Scottish Power
| 332MW | Onshore windfarm |
Under consideration | |
Crystal Rigg Extension | Natural Power
| +12.5MW | Onshore windfarm |
Under consideration | Spring 2004?
|
Cairn Uish Extension | Natural Power
| +21MW | Onshore windfarm |
Under consideration | Spring 2004?
|
Paul's Hill extension | Natural Power
| +21MW | Onshore windfarm |
Under consideration | Spring 2004?
|
Greenock | Airtricity
| 59MW | Onshore windfarm |
Under consideration | Spring 2004?
|
Gordonbush | SSE |
100MW | Onshore windfarm | Under consideration
| Spring 2004? |
Glendoe | SSE |
100MW | Hydro | Under consideration
| |
River E | Innogy |
3.0MW | Hydro | Under consideration
| |
Douglas Water | Innogy
| 3.0MW | Hydro | Under consideration
| |
Stronelairg | Innogy
| 10.3MW | Hydro | Under consideration
| |
Alt Fionn | Ambient Hydro
| 1.4MW | Hydro | Under consideration
| |
Ben Glas | Ambient Hydro
| 1.0MW | Hydro | Under consideration
| |
Fasnakyle Extension | SSE
| 7.5MW | Hydro | Under consideration
| |
Total under consideration | 1,324.7MW
| | | |
|
Note: This list is not completely comprehensive. It includes projects consented in recent years, but not SRO projects.
October 2003
| | | |
| |
|